CIV 2: Marine Construction of WTG Foundations Package
The whole project consists of 96 WTGs, WTG Foundations, Inter Array Cables and an Offshore Substation (OSS). The wind farm is located in the German Bight, 90 km west of the island of Sylt, in the German Exclusive Economic Zone (EEZ). The location provides water depths between 25 and 34 meters. The Sandbank project is equipped with an irrevocable permit. In a first construction phase 288 MW will be realized.
The scope of work of this tender includes marine construction, installation, transportation including harbour facilities of the monopiles and transition pieces for the wind turbines, including installation vessel. The time limit for the completion of this scope of work will be early 2016.