The Government of India is aiming for 175 GW of installed renewable energy capacity by 2022 out of which 160 GW will be constituted from wind and solar power systems. Two main challenges come hand in hand with high penetration of wind and solar systems installations that are variability and uncertainity. Variability and uncertainty make the generation from wind and solar PV project difficult to schedule and despatch. This causes difficulty in planning and managing overall balance of supply and demand. Additionally it imposes several other challenges in smooth grid operation and management. Green Energy Corridors (GEC) is an ambitious programme of Govt. of India to increase the capacity of Indian electricity grid to be able to take up larger amounts of electricity from variable sources of renewable energies.
Deadline
Die Frist für den Eingang der Angebote war 2017-10-02.
Die Ausschreibung wurde veröffentlicht am 2017-08-28.
Anbieter
Die folgenden Lieferanten werden in Vergabeentscheidungen oder anderen Beschaffungsunterlagen erwähnt:
Auftragsbekanntmachung (2017-08-28) Objekt Umfang der Beschaffung
Titel: Wirtschaftshilfe an das Ausland
Referenznummer: 81215501
Kurze Beschreibung:
The Government of India is aiming for 175 GW of installed renewable energy capacity by 2022 out of which 160 GW will be constituted from wind and solar power systems. Two main challenges come hand in hand with high penetration of wind and solar systems installations that are variability and uncertainity. Variability and uncertainty make the generation from wind and solar PV project difficult to schedule and despatch. This causes difficulty in planning and managing overall balance of supply and demand. Additionally it imposes several other challenges in smooth grid operation and management.
Green Energy Corridors (GEC) is an ambitious programme of Govt. of India to increase the capacity of Indian electricity grid to be able to take up larger amounts of electricity from variable sources of renewable energies.
The Government of India is aiming for 175 GW of installed renewable energy capacity by 2022 out of which 160 GW will be constituted from wind and solar power systems. Two main challenges come hand in hand with high penetration of wind and solar systems installations that are variability and uncertainity. Variability and uncertainty make the generation from wind and solar PV project difficult to schedule and despatch. This causes difficulty in planning and managing overall balance of supply and demand. Additionally it imposes several other challenges in smooth grid operation and management.
Green Energy Corridors (GEC) is an ambitious programme of Govt. of India to increase the capacity of Indian electricity grid to be able to take up larger amounts of electricity from variable sources of renewable energies.
Metadaten der Bekanntmachung
Originalsprache: Englisch 🗣️
Dokumenttyp: Auftragsbekanntmachung
Art des Auftrags: Dienstleistungen
Verordnung: Europäische Union, mit GPA-Beteiligung
Gemeinsames Vokabular für öffentliche Aufträge (CPV)
Code: Wirtschaftshilfe an das Ausland📦
Verfahren
Verfahrensart: Verhandlungsverfahren
Angebotsart: Angebot für alle Lose
Vergabekriterien
Wirtschaftlichstes Angebot
Öffentlicher Auftraggeber Identität
Land: Deutschland 🇩🇪
Art des öffentlichen Auftraggebers: Einrichtung des öffentlichen Rechts
Name des öffentlichen Auftraggebers: Deutsche Gesellschaft für Internationale Zusammenarbeit (GIZ) GmbH
Postanschrift: Dag-Hammarskjöld-Weg 1-5
Postleitzahl: 65760
Postort: Eschborn
Kontakt
Internetadresse: http://www.giz.de/procurement🌏
E-Mail: chariklia.antonoglou@giz.de📧
Telefon: +49 6196793122📞
Fax: +49 619679803122 📠
URL der Dokumente: http://www.giz.de/procurement🌏
Referenz Daten
Absendedatum: 2017-08-28 📅
Einreichungsfrist: 2017-10-02 📅
Veröffentlichungsdatum: 2017-08-29 📅
Datum des Beginns: 2018-02-15 📅
Datum des Endes: 2019-09-30 📅
Kennungen
Bekanntmachungsnummer: 2017/S 164-338286
ABl. S-Ausgabe: 164
Objekt Umfang der Beschaffung
Kurze Beschreibung:
The Government of India is aiming for 175 GW of installed renewable energy capacity by 2022 out of which 160 GW will be constituted from wind and solar power systems. Two main challenges come hand in hand with high penetration of wind and solar systems installations that are variability and uncertainity. Variability and uncertainty make the generation from wind and solar PV project difficult to schedule and despatch. This causes difficulty in planning and managing overall balance of supply and demand. Additionally it imposes several other challenges in smooth grid operation and management.
The Government of India is aiming for 175 GW of installed renewable energy capacity by 2022 out of which 160 GW will be constituted from wind and solar power systems. Two main challenges come hand in hand with high penetration of wind and solar systems installations that are variability and uncertainity. Variability and uncertainty make the generation from wind and solar PV project difficult to schedule and despatch. This causes difficulty in planning and managing overall balance of supply and demand. Additionally it imposes several other challenges in smooth grid operation and management.
Green Energy Corridors (GEC) is an ambitious programme of Govt. of India to increase the capacity of Indian electricity grid to be able to take up larger amounts of electricity from variable sources of renewable energies.
The technical cooperation component of this bilateral programme under the project ‘Green Energy Corridors’ is financed by the German Federal Ministry for Economic Cooperation & Development (BMZ) and is implemented in India by GIZ under the Indo — German Energy Programme — Green Energy Corridors (IGEN — GEC) project in cooperation with the Indian Ministry of New and Renewable Energy (MNRE).
The technical cooperation component of this bilateral programme under the project ‘Green Energy Corridors’ is financed by the German Federal Ministry for Economic Cooperation & Development (BMZ) and is implemented in India by GIZ under the Indo — German Energy Programme — Green Energy Corridors (IGEN — GEC) project in cooperation with the Indian Ministry of New and Renewable Energy (MNRE).
Under IGEN — GEC, considerable amount of work has been done on development of the concept and preparation of detailed project reports (DPRs) for the establishment of Renewable Energy Management Centres (REMCs) in the existing Load Despatch Centres(LDCs). REMCs, equipped with advanced forecasting tools/services, smart despatching solutions & real time monitoring of RE generation, can closely coordinate with the grid operations team of State LDCs / Regional LDCs / National LDC for safe, secure and optimal operations of the overall grid. The overall expected functionality of REMCs is listed as under:
Under IGEN — GEC, considerable amount of work has been done on development of the concept and preparation of detailed project reports (DPRs) for the establishment of Renewable Energy Management Centres (REMCs) in the existing Load Despatch Centres(LDCs). REMCs, equipped with advanced forecasting tools/services, smart despatching solutions & real time monitoring of RE generation, can closely coordinate with the grid operations team of State LDCs / Regional LDCs / National LDC for safe, secure and optimal operations of the overall grid. The overall expected functionality of REMCs is listed as under:
— Real time RE generation Data Acquisition and Monitoring.
— Provide RE data to its partner xLDC, forecasting and scheduling applications.
— Forecasting of RE generation (wind and solar).
— Data Archiving and Retrieval.
— Providing RE information to its concerned xLDC for dispatching and balancing RE power.
— Central Repository for RE generation data that will be used by the concerned xLDC for MIS and commercial settlement purposes.
— Coordination agency on behalf of xLDC for interacting with RE Developers.
— Training and Skill building for RE integration into the grid.
— Developing future readiness for advanced functions such as Virtual Power Plants, Storage, etc.
— All the RE related data generated and stored at the REMC at the SLDC level (except the real time RE generation) shall be sent to the RLDC and NLDC.
These REMCs are expected to be established and operational by march 2019. The objective of this assignment is therefore to enable and extend support to Power System Operator Corporation (POSOCO) and National Power Training Institute (NPTI) in designing and delivering an advanced learning programme on large scale integration of RE in India particularly focussing on topics relevant for REMCs. It is planned to conduct three complete training courses (comprising of online and face to face modules) with a maximum of thirty participants each (i.e. a total of approx. ninety participants) over the duration of the contract.
These REMCs are expected to be established and operational by march 2019. The objective of this assignment is therefore to enable and extend support to Power System Operator Corporation (POSOCO) and National Power Training Institute (NPTI) in designing and delivering an advanced learning programme on large scale integration of RE in India particularly focussing on topics relevant for REMCs. It is planned to conduct three complete training courses (comprising of online and face to face modules) with a maximum of thirty participants each (i.e. a total of approx. ninety participants) over the duration of the contract.
Ort der Leistung
Hauptstandort oder Erfüllungsort: India.
Rechtliche, wirtschaftliche, finanzielle und technische Informationen Bedingungen für die Teilnahme
Befähigung zur Berufsausübung:
Mandatory grounds for exclusion as per section 123 GWB.
Optional grounds for exclusion as per section 124 GWB.
Evicence of commercial register entry.
In case of bidding consortia: Declaration by consortium.
Wirtschaftliche und finanzielle Leistungsfähigkeit:
Average anual turnover for the last three financial years at least 900 000 EUR
number of employees as at 31.12. of the previous year at least: 10 persons.
Technische und berufliche Fähigkeiten:
The tecnical assessment is only based on reference projects with a minimum commission value of 250 000 EUR.
Mindeststandards:
At least 3 reference projects in the technical field of blended (online & classroom) capacity buidling in RE domain and at least 3 reference project in the region World.
Verfahren
Voraussichtliche Anzahl von Bewerbern: 3
Zeitpunkt des Eingangs der Angebote: 23:59
Datum der Absendung der Aufforderungen: 2017-10-16 📅
Sprachen, in denen Angebote oder Teilnahmeanträge eingereicht werden können: Englisch 🗣️
Gültigkeitsdauer des Angebots: 2018-02-14 📅
Ergänzende Informationen Körper überprüfen
Name: Bundeskartellamt, Vergabekammern des Bundes
Postanschrift: Villemomblerstr. 76
Postort: Bonn
Postleitzahl: 53123
Land: Deutschland 🇩🇪
Telefon: +49 22894990📞
Fax: +49 2289499163 📠
Internetadresse: http://www.bundeskartellamt.de🌏
Informationen zu Fristen für Nachprüfungsverfahren:
According to Article 160, Section 3 of the German Act Against Restraint of Competition, application for re-examination is not permissible insofar as
1. the applicant has identified the claimed infringement of the contract award regulations before submitting the application for re-examination and has not submitted a complaint to the commissioning party within a period of 10 calendar days; the expiry of the period pursuant to Article 134, Section 2 remains unaffected,
Informationen zu Fristen für Nachprüfungsverfahren
1. the applicant has identified the claimed infringement of the contract award regulations before submitting the application for re-examination and has not submitted a complaint to the commissioning party within a period of 10 calendar days; the expiry of the period pursuant to Article 134, Section 2 remains unaffected,
2. complaints of infringements of contract award regulations that are evident in the notice are not submitted to the commissioning party at the latest by the expiry of the deadline for the application specified in the notice or by the deadline for the submission of bids,
Informationen zu Fristen für Nachprüfungsverfahren
2. complaints of infringements of contract award regulations that are evident in the notice are not submitted to the commissioning party at the latest by the expiry of the deadline for the application specified in the notice or by the deadline for the submission of bids,
3. complaints of infringements of contract award regulations that first become evident in the tender documents are not submitted to the commissioning party at the latest by the expiry of the deadline for application or for the submission of bids,
4. more than 15 calendar days have elapsed after receipt of the notification from the commissioning party that it is unwilling to redress the complaint.
Sentence 1 does not apply in the case of an application to determine the invalidity of the contract in accordance with Article 135, Section 1 (2). Article 134, Section 1, Sentence 2 remains unaffected.
Für Mediationsverfahren zuständige Stelle Wie: Körper überprüfen
Quelle: OJS 2017/S 164-338286 (2017-08-28)
Bekanntmachung über vergebene Aufträge (2018-06-26) Objekt Umfang der Beschaffung
Kurze Beschreibung:
The Government of India is aiming for 175 GW of installed renewable energy capacity by 2022 out of which 160 GW will be constituted from wind and solar power systems. 2 main challenges come hand in hand with high penetration of wind and solar systems installations that are variability and uncertainity. Variability and uncertainty make the generation from wind and solar PV project difficult to schedule and despatch. This causes difficulty in planning and managing overall balance of supply and demand. Additionally it imposes several other challenges in smooth grid operation and management.
Green Energy Corridors (GEC) is an ambitious programme of Govt. of India to increase the capacity of Indian electricity grid to be able to take up larger amounts of electricity from variable sources of renewable energies.
The Government of India is aiming for 175 GW of installed renewable energy capacity by 2022 out of which 160 GW will be constituted from wind and solar power systems. 2 main challenges come hand in hand with high penetration of wind and solar systems installations that are variability and uncertainity. Variability and uncertainty make the generation from wind and solar PV project difficult to schedule and despatch. This causes difficulty in planning and managing overall balance of supply and demand. Additionally it imposes several other challenges in smooth grid operation and management.
Green Energy Corridors (GEC) is an ambitious programme of Govt. of India to increase the capacity of Indian electricity grid to be able to take up larger amounts of electricity from variable sources of renewable energies.
Gesamtwert des Auftrags: 628 130 EUR 💰
Metadaten der Bekanntmachung
Dokumenttyp: Bekanntmachung über vergebene Aufträge
The Government of India is aiming for 175 GW of installed renewable energy capacity by 2022 out of which 160 GW will be constituted from wind and solar power systems. 2 main challenges come hand in hand with high penetration of wind and solar systems installations that are variability and uncertainity. Variability and uncertainty make the generation from wind and solar PV project difficult to schedule and despatch. This causes difficulty in planning and managing overall balance of supply and demand. Additionally it imposes several other challenges in smooth grid operation and management.
The Government of India is aiming for 175 GW of installed renewable energy capacity by 2022 out of which 160 GW will be constituted from wind and solar power systems. 2 main challenges come hand in hand with high penetration of wind and solar systems installations that are variability and uncertainity. Variability and uncertainty make the generation from wind and solar PV project difficult to schedule and despatch. This causes difficulty in planning and managing overall balance of supply and demand. Additionally it imposes several other challenges in smooth grid operation and management.
The technical cooperation component of this bilateral programme under the project “Green Energy Corridors” is financed by the German Federal Ministry for Economic Cooperation and Development (BMZ) and is implemented in India by GIZ under the Indo – German Energy Programme – Green Energy Corridors (IGEN – GEC) project in cooperation with the Indian Ministry of New and Renewable Energy (MNRE).
The technical cooperation component of this bilateral programme under the project “Green Energy Corridors” is financed by the German Federal Ministry for Economic Cooperation and Development (BMZ) and is implemented in India by GIZ under the Indo – German Energy Programme – Green Energy Corridors (IGEN – GEC) project in cooperation with the Indian Ministry of New and Renewable Energy (MNRE).
Under IGEN – GEC, considerable amount of work has been done on development of the concept and preparation of detailed project reports (DPRs) for the establishment of Renewable Energy Management Centres (REMCs) in the existing Load Despatch Centres(LDCs). REMCs, equipped with advanced forecasting tools/services, smart despatching solutions and real time monitoring of RE generation, can closely coordinate with the grid operations team of State LDCs / Regional LDCs / National LDC for safe, secure and optimal operations of the overall grid. The overall expected functionality of REMCs is listed as under:
Under IGEN – GEC, considerable amount of work has been done on development of the concept and preparation of detailed project reports (DPRs) for the establishment of Renewable Energy Management Centres (REMCs) in the existing Load Despatch Centres(LDCs). REMCs, equipped with advanced forecasting tools/services, smart despatching solutions and real time monitoring of RE generation, can closely coordinate with the grid operations team of State LDCs / Regional LDCs / National LDC for safe, secure and optimal operations of the overall grid. The overall expected functionality of REMCs is listed as under:
— Real time RE generation Data Acquisition and Monitoring,
— Provide RE data to its partner xLDC, forecasting and scheduling applications,
— Forecasting of RE generation (wind and solar),
— Data Archiving and Retrieval,
— Providing RE information to its concerned xLDC for dispatching and balancing RE power,
— Central Repository for RE generation data that will be used by the concerned xLDC for MIS and commercial settlement purposes,
— Coordination agency on behalf of xLDC for interacting with RE Developers,
— Training and Skill building for RE integration into the grid,
Ort der Leistung
Hauptstandort oder Erfüllungsort: India
Verfahren Vergabekriterien
Qualitätskriterium (Bezeichnung): see. Technical Assessmend Grid
Qualitätskriterium (Gewichtung): 70
Kostenkriterium: see bidding conditions
Gewichtung der Kosten: 30
Auftragsvergabe
Datum des Vertragsabschlusses: 2018-06-11 📅
Ergänzende Informationen Körper überprüfen
Informationen zu Fristen für Nachprüfungsverfahren:
According to Article 160, Section 3 of the German Act Against Restraint of Competition, application for re-examination is not permissible insofar as:
1) the applicant has identified the claimed infringement of the contract award regulations before submitting the application for re-examination and has not submitted a complaint to the commissioning party within a period of 10 calendar days; the expiry of the period pursuant to Article 134, Section 2 remains unaffected;
Informationen zu Fristen für Nachprüfungsverfahren
1) the applicant has identified the claimed infringement of the contract award regulations before submitting the application for re-examination and has not submitted a complaint to the commissioning party within a period of 10 calendar days; the expiry of the period pursuant to Article 134, Section 2 remains unaffected;
2) complaints of infringements of contract award regulations that are evident in the notice are not submitted to the commissioning party at the latest by the expiry of the deadline for the application specified in the notice or by the deadline for the submission of bids;
Informationen zu Fristen für Nachprüfungsverfahren
2) complaints of infringements of contract award regulations that are evident in the notice are not submitted to the commissioning party at the latest by the expiry of the deadline for the application specified in the notice or by the deadline for the submission of bids;
3) complaints of infringements of contract award regulations that first become evident in the tender documents are not submitted to the commissioning party at the latest by the expiry of the deadline for application or for the submission of bids;
4) more than 15 calendar days have elapsed after receipt of the notification from the commissioning party that it is unwilling to redress the complaint.