The subject of this tender is the design, manufacturing, factory testing, supply, delivery, unloading, installation, on-site testing, commissioning and after sales servicing of Power Transformers and Shunt Reactors, including all necessary/ related accessories and or services for German (50Hertz) / Belgium (Elia) Onshore substations for a period of 3 years. The contract is composed of two (2) Lots. An extended description of each Lot is provided in the Selection Questionnaire (SQ) - see VI.3 for details.
Deadline
Die Frist für den Eingang der Angebote war 2023-09-13.
Die Ausschreibung wurde veröffentlicht am 2023-08-09.
Objekt Umfang der Beschaffung
Titel: Onshore Power TFO 400MVA - Shunt Reactors 33kV - FA 2024
Produkte/Dienstleistungen: Transformatoren📦
Kurze Beschreibung:
“The subject of this tender is the design, manufacturing, factory testing, supply, delivery, unloading, installation, on-site testing, commissioning and...”
Kurze Beschreibung
The subject of this tender is the design, manufacturing, factory testing, supply, delivery, unloading, installation, on-site testing, commissioning and after sales servicing of Power Transformers and Shunt Reactors, including all necessary/ related accessories and or services for German (50Hertz) / Belgium (Elia) Onshore substations for a period of 3 years. The contract is composed of two (2) Lots. An extended description of each Lot is provided in the Selection Questionnaire (SQ) - see VI.3 for details.
Mehr anzeigen Informationen über Lose
Angebote können für alle Lose eingereicht werden
Umfang der Beschaffung
Der Auftraggeber behält sich das Recht vor, Aufträge zu vergeben, die folgende Lose oder Gruppen von Losen umfassen: Will be described in the tender documents.
1️⃣ Umfang der Beschaffung
Titel:
“Power Transformers Um ≤ 420kV / Sr ≥ 200MVA for German (50Hertz) Onshore Substations” Titel
Los-Identifikationsnummer: 1
Beschreibung
Zusätzliche Produkte/Dienstleistungen: Transformatoren📦
Ort der Leistung: Deutschland🏙️
Hauptstandort oder Erfüllungsort: Germany
Beschreibung der Beschaffung:
“The subject of this tender is the design, manufacturing, factory testing, supply, transport, delivery, unloading, installation, on-site testing,...”
Beschreibung der Beschaffung
The subject of this tender is the design, manufacturing, factory testing, supply, transport, delivery, unloading, installation, on-site testing, commissioning and after sales servicing of Power Transformers Um ≤ 420kV / Sr ≥ 200MVA, including all necessary/related accessories and or services for German (50Hertz) Onshore substations for a period of 3 years. An extended description of this Lot is provided in the Selection Questionnaire (SQ) – see VI.3 for details.
Estimated quantities (units) : approx. 60 units (+ additional 100%)
The contracting entity reserves the right to organize mini-competition(s) between the awarded suppliers in case new projects with a similar scope arise within Elia Group.
Mehr anzeigen Vergabekriterien
Der Preis ist nicht das einzige Zuschlagskriterium, und alle Kriterien werden nur in den Auftragsunterlagen genannt
Laufzeit des Vertrags, der Rahmenvereinbarung oder des dynamischen Beschaffungssystems
Der nachstehende Zeitrahmen ist in Monaten ausgedrückt.
Beschreibung
Dauer: 36
Informationen über Optionen
Optionen ✅
Beschreibung der Optionen: If applicable, will be described in the tender documents
Beschreibung
Zusätzliche Informationen:
“If a Candidate applying with 1 or more production factory(ies) new to the Contracting Authority is awarded, 50Hertz reserves the right to subject them to a...”
Zusätzliche Informationen
If a Candidate applying with 1 or more production factory(ies) new to the Contracting Authority is awarded, 50Hertz reserves the right to subject them to a Qualification Phase.
During this Qualification Phase, the quantity of units ordered could be limited for a period of 1 year from the energizing of all ordered units.
More details on qualification phase will be given in the tender documents.
2️⃣ Umfang der Beschaffung
Titel: Shunt Reactors Um ≤ 36kV / Qr ≤ 90MVAR for German (50Hertz) Onshore Substations
Titel
Los-Identifikationsnummer: 2
Beschreibung
Beschreibung der Beschaffung:
“The subject of this tender is the design, manufacturing, factory testing, supply, transport, delivery, unloading, installation, on-site testing,...”
Beschreibung der Beschaffung
The subject of this tender is the design, manufacturing, factory testing, supply, transport, delivery, unloading, installation, on-site testing, commissioning and after sales servicing of Shunt Reactors Um ≤ 36 kV / Qr ≤ 90MVAR, including all necessary/related accessories and or services for German (50Hertz) Onshore substations for a period of 3 years. An extended description of this Lot is provided in the Selection Questionnaire (SQ) – see VI.3 for details.
Estimated quantities (units) : approx. 20 units (+ additional 100%)
The contracting entity reserves the right to organize mini-competition(s) between the awarded suppliers in case new projects with a similar scope arise within Elia Group.
Mehr anzeigen Informationen über Optionen
Beschreibung der Optionen: If applicable, will be described in the tender documents.
Rechtliche, wirtschaftliche, finanzielle und technische Informationen Wirtschaftliche und finanzielle Leistungsfähigkeit
Liste und kurze Beschreibung der Auswahlkriterien:
“Selection criteria as stated in the Selection Questionnaire.
https://eliagroup.sharepoint.com/:f:/s/EFSS/EFSS/EuaTRjOmyL5Cniv6mexMZgQBhPae8OVx57WzLTkvfTMk2A?e=MMy3qe”
Mehr anzeigen Technische und berufliche Fähigkeiten
Liste und kurze Beschreibung der Auswahlkriterien:
“Selection criteria as stated in the Selection Questionnaire.
https://eliagroup.sharepoint.com/:f:/s/EFSS/EFSS/EuaTRjOmyL5Cniv6mexMZgQBhPae8OVx57WzLTkvfTMk2A?e=MMy3qe”
Verfahren Art des Verfahrens
Verhandlungsverfahren mit vorherigem Aufruf zum Wettbewerb
Informationen über eine Rahmenvereinbarung oder ein dynamisches Beschaffungssystem
Rahmenvereinbarung mit mehreren Betreibern
Informationen über die Reduzierung der Anzahl von Lösungen oder Angeboten während der Verhandlungen oder des Dialogs
Rückgriff auf ein gestaffeltes Verfahren, um die Zahl der zu erörternden Lösungen oder zu verhandelnden Angebote schrittweise zu verringern
Administrative Informationen
Frist für den Eingang von Angeboten oder Teilnahmeanträgen: 2023-09-13 📅
Sprachen, in denen Angebote oder Teilnahmeanträge eingereicht werden können: Englisch 🗣️
Sprachen, in denen Angebote oder Teilnahmeanträge eingereicht werden können: Deutsch 🗣️
“Pursuant to Article 29 of Regulation (EU) 2022/2560 (the “Regulation”), economic operators participating in the Tender within the meaning of Articles 2(1)...”
Pursuant to Article 29 of Regulation (EU) 2022/2560 (the “Regulation”), economic operators participating in the Tender within the meaning of Articles 2(1) and 29(5) of the Regulation must, (1) together with the request to participate and (2) together with the final bid:
1. submit a notification to the Employer in accordance with Article 29(1) of the Regulation listing all foreign financial contributions within the meaning of Articles 3, 28(1) and 28(2) of the Regulation. This notification shall be submitted to the Employer in the form set out in Annex II to the European Commission’s implementing Regulation (EU) 2023/1441; or
2. if the notifying parties did not receive any notifiable foreign financial contributions:
a) submit a declaration to the Employer in accordance with Article 29(1) of the Regulation; and
b) submit a list of all foreign financial contributions received; and
c) submit a statement confirming that none of the participating notifying party(ies) have received foreign financial contributions notifiable under Chapter 4 of the Regulation.
The declaration or statement shall be submitted to the Employer in the form set out in Annex II to the European Commission’s implementing Regulation (EU) 2023/1441.
Pursuant to Article 29(5) of the Regulation, the obligation to notify foreign financial contributions applies to:
• economic operators, groups of economic operators within the meaning of Article 37(2) of Directive 2014/25/EU; and
• main subcontractors and main suppliers within the meaning of Article 29(5) of the Regulation.
The main contractor within the meaning of Directive 2014/25/EU shall ensure the submission of the notification or declaration. Failure to submit the notification or declaration will be treated in accordance with Article 29(3) of the Regulation
The Candidate must request, complete and submit by the closing date (see IV.2.2.) the Selection Questionnaire (SQ) with the most actual available data together with the requested documents.
The applicants must request the access to the tender on the Ariba platform by sending an e-mail to the responsible buyer (see I.1.) mentioning the name of the legal entity, address, VAT number, name + e-mail + telephone of the contact(s).
Information to access the tender on the Ariba platform will be provided by e-mail as soon as possible.
Applicants are advised to request this access as soon as possible and to click on ‘intend to participate’ in Ariba in order to receive possible clarifications from the contracting entity.
Contracting entity don’t guaranty to provide the Ariba login details before closing time for candidates requesting their access to Ariba less than 72 hours before closing time.
The applicant is solely responsible for requesting the access to the tender on the Ariba platform on time.
The contracting entity declines any responsibility in the event of problems with the Ariba platform.
Any application not sent correctly via Ariba will be rejected.
The manuals for usage of E-Sourcing (Ariba) can be found via the following URL:
http://www.elia.be/en/suppliers/information-and-tools-for-suppliers#ariba
Mehr anzeigen Körper überprüfen
Name: Vergabekammer des Landes Berlin
Postanschrift: Martin-Luther-Straße 105
Postort: Berlin
Postleitzahl: 10825
Land: Deutschland 🇩🇪
Telefon: +49 3090138316📞
E-Mail: vergabekammer@senweb.berlin.de📧
Fax: +49 3090137613 📠
URL: https://www.berlin.de/sen/wirtschaft/wirtschaft/wirtschaftsrecht/vergabekammer🌏 Verfahren zur Überprüfung
Genaue Informationen über Fristen für Überprüfungsverfahren:
“Deadlines for submitting an application for review are set out in Section 160 (3) GWB. . For clarification, this provision is reproduced in full. “The...”
Genaue Informationen über Fristen für Überprüfungsverfahren
Deadlines for submitting an application for review are set out in Section 160 (3) GWB. . For clarification, this provision is reproduced in full. “The application is inadmissible if 1. the applicant became aware of the claimed violation of public procurement provisions before filing the application for review, but did not complain to the contracting authority within a time limit of 10 calendar days; the expiry of the time limit under § 134(2) remains unaffected, 2. violations of public procurement provisions which become apparent from the tender notice are not notified to the contracting authority by the end of the time limit for the application or the submission of a tender specified in the notice, 3. violations of public procurement provisions which only become apparent from the procurement documents are not notified to the contracting authority by the end of the time limit for the application or the submission of a tender specified in the notice, 4. more than 15 calendar days have expired since receipt of notification from the contracting authority that it is unwilling to redress the objection.
Mehr anzeigen
Quelle: OJS 2023/S 155-493760 (2023-08-09)
Ergänzende Angaben (2023-09-15)
Ergänzende Informationen Referenz der ursprünglichen Mitteilung
Nummer der Bekanntmachung im Amtsblatt S: 2023/S 155-493760
Änderungen Zu berichtigender Text in der ursprünglichen Bekanntmachung
Nummer des Abschnitts: VI.3
Alter Wert
Text:
“Pursuant to Article 29 of Regulation (EU) 2022/2560 (the “Regulation”), economic operators participating in the Tender within the meaning of Articles 2(1)...”
Text
Pursuant to Article 29 of Regulation (EU) 2022/2560 (the “Regulation”), economic operators participating in the Tender within the meaning of Articles 2(1) and 29(5) of the Regulation must, (1) together with the request to participate and (2) together with the final bid:
1. submit a notification to the Employer in accordance with Article 29(1) of the Regulation listing all foreign financial contributions within the meaning of Articles 3, 28(1) and 28(2) of the Regulation. This notification shall be submitted to the Employer in the form set out in Annex II to the European Commission’s implementing Regulation (EU) 2023/1441; or
2. if the notifying parties did not receive any notifiable foreign financial contributions:
a) submit a declaration to the Employer in accordance with Article 29(1) of the Regulation; and
b) submit a list of all foreign financial contributions received; and
c) submit a statement confirming that none of the participating notifying party(ies) have received foreign financial contributions notifiable under Chapter 4 of the Regulation.
The declaration or statement shall be submitted to the Employer in the form set out in Annex II to the European Commission’s implementing Regulation (EU) 2023/1441.
Pursuant to Article 29(5) of the Regulation, the obligation to notify foreign financial contributions applies to:
• economic operators, groups of economic operators within the meaning of Article 37(2) of Directive 2014/25/EU; and
• main subcontractors and main suppliers within the meaning of Article 29(5) of the Regulation.
The main contractor within the meaning of Directive 2014/25/EU shall ensure the submission of the notification or declaration. Failure to submit the notification or declaration will be treated in accordance with Article 29(3) of the Regulation
The Candidate must request, complete and submit by the closing date (see IV.2.2.) the Selection Questionnaire (SQ) with the most actual available data together with the requested documents.
The applicants must request the access to the tender on the Ariba platform by sending an e-mail to the responsible buyer (see I.1.) mentioning the name of the legal entity, address, VAT number, name + e-mail + telephone of the contact(s).
Information to access the tender on the Ariba platform will be provided by e-mail as soon as possible.
Applicants are advised to request this access as soon as possible and to click on ‘intend to participate’ in Ariba in order to receive possible clarifications from the contracting entity.
Contracting entity don’t guaranty to provide the Ariba login details before closing time for candidates requesting their access to Ariba less than 72 hours before closing time.
The applicant is solely responsible for requesting the access to the tender on the Ariba platform on time.
The contracting entity declines any responsibility in the event of problems with the Ariba platform.
Any application not sent correctly via Ariba will be rejected.
The manuals for usage of E-Sourcing (Ariba) can be found via the following URL:
https://www.elia.be/en/suppliers/information-and-tools#ariba
Mehr anzeigen Neuer Wert
Text:
“The Candidate must request, complete and submit by the closing date (see IV.2.2.) the Selection Questionnaire (SQ) with the most actual available data...”
Text
The Candidate must request, complete and submit by the closing date (see IV.2.2.) the Selection Questionnaire (SQ) with the most actual available data together with the requested documents.
The applicants must request the access to the tender on the Ariba platform by sending an e-mail to the responsible buyer (see I.1.) mentioning the name of the legal entity, address, VAT number, name + e-mail + telephone of the contact(s).
Information to access the tender on the Ariba platform will be provided by e-mail as soon as possible.
Applicants are advised to request this access as soon as possible and to click on ‘intend to participate’ in Ariba in order to receive possible clarifications from the contracting entity.
Contracting entity don’t guaranty to provide the Ariba login details before closing time for candidates requesting their access to Ariba less than 72 hours before closing time.
The applicant is solely responsible for requesting the access to the tender on the Ariba platform on time.
The contracting entity declines any responsibility in the event of problems with the Ariba platform.
Any application not sent correctly via Ariba will be rejected.
The manuals for usage of E-Sourcing (Ariba) can be found via the following URL:
http://www.elia.be/en/suppliers/information-and-tools-for-suppliers#ariba
Mehr anzeigen Andere zusätzliche Informationen
Please Note Article 29 EU 2022/2560 is not applicable for the Selection Phase.
Quelle: OJS 2023/S 181-565298 (2023-09-15)