Water supply measures. Supply, delivery and installation of pipework material, for transmission mains with approximately length of 2,0 km (DCI DN 700 mm) and distribution pipes (Pipes PE-100 OD 75 — OD 450) approximately overall length of 42 km, electrofusion fittings, ductile iron fittings, valves, domestic water meter, bulk water meter and check valves plus the installation of service connections (approx. 6 635 Pcs – PE-RC OD 20 – OD 63 mm, length 45 km). Rehabilitation of mechanical parts of 1 reservoir. Update of existing SCADA System. Sewage measures: Supply, delivery and installation of sewerage pipes (corrugated PE SN 8) for sewerage collectors with approx. length of 12,5 km and service connections (1 500 Pcs DN 100 – DN 250) and fittings, connectors and PE manholes (various diameter) for sewage collectors and service connections.
Deadline
Die Frist für den Eingang der Angebote war 2019-06-12.
Die Ausschreibung wurde veröffentlicht am 2019-04-26.
Auftragsbekanntmachung (2019-04-26) Objekt Umfang der Beschaffung
Titel: Wasserzähler
Kurze Beschreibung:
Water supply measures.
Supply, delivery and installation of pipework material, for transmission mains with approximately length of 2,0 km (DCI DN 700 mm) and distribution pipes (Pipes PE-100 OD 75 — OD 450) approximately overall length of 42 km, electrofusion fittings, ductile iron fittings, valves, domestic water meter, bulk water meter and check valves plus the installation of service connections (approx. 6 635 Pcs – PE-RC OD 20 – OD 63 mm, length 45 km). Rehabilitation of mechanical parts of 1 reservoir. Update of existing SCADA System.
Sewage measures:
Supply, delivery and installation of sewerage pipes (corrugated PE SN 8) for sewerage collectors with approx. length of 12,5 km and service connections (1 500 Pcs DN 100 – DN 250) and fittings, connectors and PE manholes (various diameter) for sewage collectors and service connections.
Supply, delivery and installation of pipework material, for transmission mains with approximately length of 2,0 km (DCI DN 700 mm) and distribution pipes (Pipes PE-100 OD 75 — OD 450) approximately overall length of 42 km, electrofusion fittings, ductile iron fittings, valves, domestic water meter, bulk water meter and check valves plus the installation of service connections (approx. 6 635 Pcs – PE-RC OD 20 – OD 63 mm, length 45 km). Rehabilitation of mechanical parts of 1 reservoir. Update of existing SCADA System.
Sewage measures:
Supply, delivery and installation of sewerage pipes (corrugated PE SN 8) for sewerage collectors with approx. length of 12,5 km and service connections (1 500 Pcs DN 100 – DN 250) and fittings, connectors and PE manholes (various diameter) for sewage collectors and service connections.
Metadaten der Bekanntmachung
Originalsprache: Englisch 🗣️
Dokumenttyp: Auftragsbekanntmachung
Art des Auftrags: Bauleistung
Verordnung: Europäische Union
Gemeinsames Vokabular für öffentliche Aufträge (CPV)
Code: Wasserzähler📦
Zusätzlicher CPV-Code: Wasserinstallationen📦 Ort der Leistung
NUTS-Region: Schweiz/Suisse/Svizzera
🏙️
Verfahren
Verfahrensart: Offenes Verfahren
Angebotsart: Angebot für alle Lose
Vergabekriterien
Wirtschaftlichstes Angebot
Öffentlicher Auftraggeber Identität
Land: Deutschland 🇩🇪
Art des öffentlichen Auftraggebers: Ministerium oder sonstige zentral- oder bundesstaatliche Behörde
Name des öffentlichen Auftraggebers: p2mberlin GmbH
Postanschrift: Huttenstrasse 34/35
Postleitzahl: 10553
Postort: Berlin
Kontakt
Internetadresse: https://www.simap.ch🌏
E-Mail: info@p2mberlin.de📧
URL der Dokumente: http://www.simap.ch/shabforms/servlet/Search?NOTICE_NR=1070237🌏
Partial offers are not permitted.
Conditions for countries not party to the WTO agreement: None.
Negotiations: remain reserved.
Additional information: The MIP III is co-financed by the Swiss Confederation through the State Secretariat of Economic Affairs (SECO).
Remarks (Desired deadline for questions in written form) Attention: Clarification requests shall be submitted via e-mail to carsten.reimers@p2mberlin.de. Answers to the clarification requests will be returned anonymized via e-mail to all bidders.
National reference publication: Simap of 26.4.2019, doc. 1070237. Desired deadline for questions in written form: 29.5.2019.
Conditions of payment: Receipt of payment at indicated account number or cash payment in amount of 150 EUR.
Costs: 150,00 EUR.
Conditions for countries not party to the WTO agreement: None.
Negotiations: remain reserved.
Additional information: The MIP III is co-financed by the Swiss Confederation through the State Secretariat of Economic Affairs (SECO).
Remarks (Desired deadline for questions in written form) Attention: Clarification requests shall be submitted via e-mail to carsten.reimers@p2mberlin.de. Answers to the clarification requests will be returned anonymized via e-mail to all bidders.
National reference publication: Simap of 26.4.2019, doc. 1070237. Desired deadline for questions in written form: 29.5.2019.
Conditions of payment: Receipt of payment at indicated account number or cash payment in amount of 150 EUR.
Costs: 150,00 EUR.
Objekt Umfang der Beschaffung
Kurze Beschreibung:
Water supply measures.
Supply, delivery and installation of pipework material, for transmission mains with approximately length of 2,0 km (DCI DN 700 mm) and distribution pipes (Pipes PE-100 OD 75 — OD 450) approximately overall length of 42 km, electrofusion fittings, ductile iron fittings, valves, domestic water meter, bulk water meter and check valves plus the installation of service connections (approx. 6 635 Pcs – PE-RC OD 20 – OD 63 mm, length 45 km). Rehabilitation of mechanical parts of 1 reservoir. Update of existing SCADA System.
Supply, delivery and installation of pipework material, for transmission mains with approximately length of 2,0 km (DCI DN 700 mm) and distribution pipes (Pipes PE-100 OD 75 — OD 450) approximately overall length of 42 km, electrofusion fittings, ductile iron fittings, valves, domestic water meter, bulk water meter and check valves plus the installation of service connections (approx. 6 635 Pcs – PE-RC OD 20 – OD 63 mm, length 45 km). Rehabilitation of mechanical parts of 1 reservoir. Update of existing SCADA System.
Sewage measures:
Supply, delivery and installation of sewerage pipes (corrugated PE SN 8) for sewerage collectors with approx. length of 12,5 km and service connections (1 500 Pcs DN 100 – DN 250) and fittings, connectors and PE manholes (various diameter) for sewage collectors and service connections.
Supply, delivery and installation of sewerage pipes (corrugated PE SN 8) for sewerage collectors with approx. length of 12,5 km and service connections (1 500 Pcs DN 100 – DN 250) and fittings, connectors and PE manholes (various diameter) for sewage collectors and service connections.
Dauer: 24 Monate Ort der Leistung
Hauptstandort oder Erfüllungsort:
Berat, ALBANIA.
Kucova, ALBANIA.
Verfahren
Rechtsgrundlage: 32014L0024
Sprachen, in denen Angebote oder Teilnahmeanträge eingereicht werden können: Englisch 🗣️
Datum der Angebotseröffnung: 2019-06-12 📅
Zeitpunkt der Angebotseröffnung: 23:59
Conditions for countries not party to the WTO agreement: None.
Negotiations: remain reserved.
Additional information: The MIP III is co-financed by the Swiss Confederation through the State Secretariat of Economic Affairs (SECO).
Remarks (Desired deadline for questions in written form) Attention: Clarification requests shall be submitted via e-mail to carsten.reimers@p2mberlin.de. Answers to the clarification requests will be returned anonymized via e-mail to all bidders.
National reference publication: Simap of 26.4.2019, doc. 1070237. Desired deadline for questions in written form: 29.5.2019.
Conditions of payment: Receipt of payment at indicated account number or cash payment in amount of 150 EUR.