The wind farm Nordsee One (N1) is located in the German Bight, approximately 32 km north of the island Juist. The water depth ranges roughly between 26 m and 34 m (LAT) with 2,7 m tidal range. Under operation are 54 Senvion wind turbine generators (WTG) of 6.2M126 type with a nominal output of 6.15 MW. The WTGs are erected on monopile foundations and the substation on a jacket foundation. N1 wants to enter into a Service- and Maintenance Agreement (SMA) for the Balance of Plant (BoP) (offshore substation, its jacket foundation and monopile foundations) with a long-term full-scope service, starting from 1 November 2022 until 31 October 2027. The main tasks of the scope will be maintenance (scheduled and unscheduled), inspection and repair of components including major components, management of spare parts, documentation and reporting of the tasks and all tasks which are necessary to keep the wind farm running safe and sustainable, while at the same time keeping the level of downtimes as low as possible and through a preventive maintenance approach schedule downtimes in time of low wind speed and other scheduled outages, like the TenneT platform, that provides the wind farm's grid connection. The scope shall include full logistics, base infrastructure, spare part procurement, monitoring, and control.
Deadline
Die Frist für den Eingang der Angebote war 2022-01-18.
Die Ausschreibung wurde veröffentlicht am 2021-12-17.
Auftragsbekanntmachung (2021-12-17) Objekt Umfang der Beschaffung
Titel: Bauinstallationsarbeiten
Referenznummer: 4564/2021
Kurze Beschreibung:
The wind farm Nordsee One (N1) is located in the German Bight, approximately 32 km north of the island Juist. The water depth ranges roughly between 26 m and 34 m (LAT) with 2,7 m tidal range. Under operation are 54 Senvion wind turbine generators (WTG) of 6.2M126 type with a nominal output of 6.15 MW. The WTGs are erected on monopile foundations and the substation on a jacket foundation.
N1 wants to enter into a Service- and Maintenance Agreement (SMA) for the Balance of Plant (BoP) (offshore substation, its jacket foundation and monopile foundations) with a long-term full-scope service, starting from 1 November 2022 until 31 October 2027. The main tasks of the scope will be maintenance (scheduled and unscheduled), inspection and repair of components including major components, management of spare parts, documentation and reporting of the tasks and all tasks which are necessary to keep the wind farm running safe and sustainable, while at the same time keeping the level of downtimes as low as possible and through a preventive maintenance approach schedule downtimes in time of low wind speed and other scheduled outages, like the TenneT platform, that provides the wind farm's grid connection. The scope shall include full logistics, base infrastructure, spare part procurement, monitoring, and control.
The wind farm Nordsee One (N1) is located in the German Bight, approximately 32 km north of the island Juist. The water depth ranges roughly between 26 m and 34 m (LAT) with 2,7 m tidal range. Under operation are 54 Senvion wind turbine generators (WTG) of 6.2M126 type with a nominal output of 6.15 MW. The WTGs are erected on monopile foundations and the substation on a jacket foundation.
N1 wants to enter into a Service- and Maintenance Agreement (SMA) for the Balance of Plant (BoP) (offshore substation, its jacket foundation and monopile foundations) with a long-term full-scope service, starting from 1 November 2022 until 31 October 2027. The main tasks of the scope will be maintenance (scheduled and unscheduled), inspection and repair of components including major components, management of spare parts, documentation and reporting of the tasks and all tasks which are necessary to keep the wind farm running safe and sustainable, while at the same time keeping the level of downtimes as low as possible and through a preventive maintenance approach schedule downtimes in time of low wind speed and other scheduled outages, like the TenneT platform, that provides the wind farm's grid connection. The scope shall include full logistics, base infrastructure, spare part procurement, monitoring, and control.
Metadaten der Bekanntmachung
Originalsprache: Deutsch 🗣️
Dokumenttyp: Auftragsbekanntmachung
Art des Auftrags: Bauleistung
Verordnung: Europäische Union, mit GPA-Beteiligung
Gemeinsames Vokabular für öffentliche Aufträge (CPV)
Code: Bauinstallationsarbeiten📦
Zusätzlicher CPV-Code: Reparatur- und Wartungsdienste📦 Ort der Leistung
NUTS-Region: Stormarn
🏙️
Verfahren
Verfahrensart: Verhandlungsverfahren
Angebotsart: Angebot für alle Lose
Vergabekriterien
Wirtschaftlichstes Angebot
Referenz Daten
Absendedatum: 2021-12-17 📅
Einreichungsfrist: 2022-01-18 📅
Veröffentlichungsdatum: 2021-12-22 📅
Datum des Beginns: 2022-11-01 📅
Datum des Endes: 2027-10-31 📅
Kennungen
Bekanntmachungsnummer: 2021/S 248-657921
ABl. S-Ausgabe: 248
Zusätzliche Informationen
Bekanntmachungs-ID: CXP4YYVRAT9
Objekt Umfang der Beschaffung
Kurze Beschreibung:
The wind farm Nordsee One (N1) is located in the German Bight, approximately 32 km north of the island Juist. The water depth ranges roughly between 26 m and 34 m (LAT) with 2,7 m tidal range. Under operation are 54 Senvion wind turbine generators (WTG) of 6.2M126 type with a nominal output of 6.15 MW. The WTGs are erected on monopile foundations and the substation on a jacket foundation.
The wind farm Nordsee One (N1) is located in the German Bight, approximately 32 km north of the island Juist. The water depth ranges roughly between 26 m and 34 m (LAT) with 2,7 m tidal range. Under operation are 54 Senvion wind turbine generators (WTG) of 6.2M126 type with a nominal output of 6.15 MW. The WTGs are erected on monopile foundations and the substation on a jacket foundation.
N1 wants to enter into a Service- and Maintenance Agreement (SMA) for the Balance of Plant (BoP) (offshore substation, its jacket foundation and monopile foundations) with a long-term full-scope service, starting from 1 November 2022 until 31 October 2027. The main tasks of the scope will be maintenance (scheduled and unscheduled), inspection and repair of components including major components, management of spare parts, documentation and reporting of the tasks and all tasks which are necessary to keep the wind farm running safe and sustainable, while at the same time keeping the level of downtimes as low as possible and through a preventive maintenance approach schedule downtimes in time of low wind speed and other scheduled outages, like the TenneT platform, that provides the wind farm's grid connection. The scope shall include full logistics, base infrastructure, spare part procurement, monitoring, and control.
N1 wants to enter into a Service- and Maintenance Agreement (SMA) for the Balance of Plant (BoP) (offshore substation, its jacket foundation and monopile foundations) with a long-term full-scope service, starting from 1 November 2022 until 31 October 2027. The main tasks of the scope will be maintenance (scheduled and unscheduled), inspection and repair of components including major components, management of spare parts, documentation and reporting of the tasks and all tasks which are necessary to keep the wind farm running safe and sustainable, while at the same time keeping the level of downtimes as low as possible and through a preventive maintenance approach schedule downtimes in time of low wind speed and other scheduled outages, like the TenneT platform, that provides the wind farm's grid connection. The scope shall include full logistics, base infrastructure, spare part procurement, monitoring, and control.
See Call for Competition (CfC) for further detail
Bezeichnung des von der EU finanzierten Projekts oder Programms: NER 300
Ort der Leistung
Hauptstandort oder Erfüllungsort: Offshore Wind Farm Nordsee One
Rechtliche, wirtschaftliche, finanzielle und technische Informationen Bedingungen für die Teilnahme
Befähigung zur Berufsausübung:
Extract from the commercial register (or comparable document) if
registration in such a register is required by law according to the candidate's or the members of the consortium's country of origin
Wirtschaftliche und finanzielle Leistungsfähigkeit:
Description of the candidate's or the members' of the consortium's legal structure and liability
Candidate's or members' of the consortium equity ratio of the last three financial years
Candidate's or members' of the consortium profit & loss (yearly results of the last three financial years)
Commitment to provide performance bond for the offered / contracted services and warranties
Technische und berufliche Fähigkeiten:
Company presentation (qualified personnel, relevant technical equipment etc.)
Presentation of references for comparable services
HSE statistic for the last three years (summarizing the number of lost time incidents (LTI) per hours worked as well as the number of total recordable incidents) - exclusion at LTI bigger than 4 in average
Information on the Management Systems for QHSE, together with proof for the relevant certification. If no certification might be available, the candidate shall provide a presentation and / or general information on the status of the management systems and (if planned) a milestone schedule for the certification process.
Information on the Management Systems for QHSE, together with proof for the relevant certification. If no certification might be available, the candidate shall provide a presentation and / or general information on the status of the management systems and (if planned) a milestone schedule for the certification process.
Mindeststandards: Exclusion at LTI bigger than 4 in average
Liste und kurze Beschreibung der Regeln und Kriterien: See CfC for further detail
Auftragsausführung
Geforderte Kautionen und Garantien: See CfC for further detail
Wichtigste Finanzierungsbedingungen und Zahlungsmodalitäten und/oder Verweis auf die einschlägigen Bestimmungen, die sie regeln: See CfC for further detail
Rechtsform der Gruppe von Wirtschaftsteilnehmern, an die der Auftrag vergeben werden soll: See CfC for further detail
Bedingungen für die Vertragserfüllung: See CfC for further detail
Verfahren
Rechtsgrundlage: 32014L0025
Voraussichtliche Anzahl von Bewerbern: 5
Objektive Kriterien für die Auswahl der begrenzten Anzahl von Bewerbern: See Call for Competition (CfC) for further detail
Zeitpunkt des Eingangs der Angebote: 11:00
Datum der Absendung der Aufforderungen: 2022-02-07 📅
Sprachen, in denen Angebote oder Teilnahmeanträge eingereicht werden können: Deutsch 🗣️
Englisch 🗣️
Gültigkeitsdauer des Angebots: 2 Monate
Referenz Zusätzliche Informationen
Voraussichtlicher Zeitpunkt weiterer Bekanntmachungen: Dezember 2026
Ergänzende Informationen Körper überprüfen
Name: See para 5 CfC
Postort: See para 6 CfC
Land: Deutschland 🇩🇪
Quelle: OJS 2021/S 248-657921 (2021-12-17)