This tender contains a binding scope of seven on- and offshore connections with 525 kV HVDC power cables on basis of EPCI-contracts. The four offshore and three onshore projects are divided into three lots (1 - 3) containing an overall binding volume of 3.536 km core cable length. Additionally the contracting Entity is awarding a lot (Lot 7) with optional volume for future projects with an expected volume of 900 km core cable length and a maximum volume of 2.700 km core cable length. The complete scope of Works is included in the (individual) lots 1, 2 and 3 (commitment to purchase by the Contracting Entity) and lot 7 (no commitment to call-off by the Contracting Entity). Lots 4 – 6 are combinations of lots 1 – 3, each comprising two lots from 1 - 3. It is clarified, that the scope of Works in the (individual) lots 1, 2 and 3 is identical to the scope of works of combination lots 4, 5 and 6 and that the scope of works will only be awarded once.
Deadline
Die Frist für den Eingang der Angebote war 2023-01-27.
Die Ausschreibung wurde veröffentlicht am 2022-12-23.
Auftragsbekanntmachung (2022-12-23) Objekt Umfang der Beschaffung
Titel: Hochspannungskabel
Kurze Beschreibung:
This tender contains a binding scope of seven on- and offshore connections with 525 kV HVDC power cables on basis of EPCI-contracts. The four offshore and three onshore projects are divided into three lots (1 - 3) containing an overall binding volume of 3.536 km core cable length. Additionally the contracting Entity is awarding a lot (Lot 7) with optional volume for future projects with an expected volume of 900 km core cable length and a maximum volume of 2.700 km core cable length.
The complete scope of Works is included in the (individual) lots 1, 2 and 3 (commitment to purchase by the Contracting Entity) and lot 7 (no commitment to call-off by the Contracting Entity). Lots 4 – 6 are combinations of lots 1 – 3, each comprising two lots from 1 - 3. It is clarified, that the scope of Works in the (individual) lots 1, 2 and 3 is identical to the scope of works of combination lots 4, 5 and 6 and that the scope of works will only be awarded once.
This tender contains a binding scope of seven on- and offshore connections with 525 kV HVDC power cables on basis of EPCI-contracts. The four offshore and three onshore projects are divided into three lots (1 - 3) containing an overall binding volume of 3.536 km core cable length. Additionally the contracting Entity is awarding a lot (Lot 7) with optional volume for future projects with an expected volume of 900 km core cable length and a maximum volume of 2.700 km core cable length.
The complete scope of Works is included in the (individual) lots 1, 2 and 3 (commitment to purchase by the Contracting Entity) and lot 7 (no commitment to call-off by the Contracting Entity). Lots 4 – 6 are combinations of lots 1 – 3, each comprising two lots from 1 - 3. It is clarified, that the scope of Works in the (individual) lots 1, 2 and 3 is identical to the scope of works of combination lots 4, 5 and 6 and that the scope of works will only be awarded once.
Metadaten der Bekanntmachung
Originalsprache: Englisch 🗣️
Dokumenttyp: Auftragsbekanntmachung
Art des Auftrags: Lieferungen
Verordnung: Europäische Union, mit GPA-Beteiligung
Gemeinsames Vokabular für öffentliche Aufträge (CPV)
Code: Hochspannungskabel📦
Zusätzlicher CPV-Code: Hochspannungskabel📦 Ort der Leistung
NUTS-Region: Deutschland
🏙️
Belgique/België
🏙️
Verfahren
Verfahrensart: Verhandlungsverfahren
Angebotsart: Angebot für alle Lose
Vergabekriterien
Wirtschaftlichstes Angebot
1) In case a candidate relies on capacities, especially references, of other entities (subcontractors) to fulfill one or more selection criteria this subcontractor can be exchanged in the execution phase according to the conditions set-out in the contract, especially also fulfills the said selection criteria.
2) In case of an application of a consortium, the Contracting Entity accepts, that the Consortium partner, who fulfills the criteria for cable design and manufacture but not the criteria for installation may execute the contract without the other consortium partner or with a new consortium partner.
3) The non-confidential part of the tender package is directly available to applicants via the weblink mentioned under section I.3) of the contract notice.
4) Access to the confidential part of the tender package will be granted to the selected candidates as further set out in the invitation to tender (ITT).
5) Information to access the tender on the Ariba platform will be provided by e-mail as soon as possible. Applicants are advised to request this access as soon as possible and to click on ‘intend to participate’ in Ariba in order to receive possible clarifications from the contracting entity. The applicant must request, complete and submit by the closing date (see IV.2.2.) the selection questionnaire (SQ) with the most current available data together with the requested documents. Contracting entity doesn’t guarantee to provide the Ariba login details before closing time for candidates requesting their access to Ariba less than 48 hours before closing time.The applicant is solely responsible for requesting the access to the tender on the Ariba platform on time.The contracting entity declines any responsibility in the event of problems with the Ariba platform. Any application not sent correctly via Ariba will be rejected. The manuals for usage of E-Sourcing (Ariba) can be found via the following URL: http://www.elia.be/en/suppliers/information-and-tools-for-suppliers#ariba
6) Next to the Contracting Entities mentioned in I.1) also companies currently and in future belonging to the Elia Group may call-off the works of Lots 1 – 7. In addition, the Contracting Entity is planning to foresee in the right to interchange projects between and inside the lots according to the conditions set-up in the contract.
7) The Contracting Entity points out, that for Lots 1 – 6 a PQ-test at time of the BAFO is a mandatory condition for award. For Lot 7 a PQ-test is a mandatory condition at the time of the call-off and must therefore not yet be present at the time of the BAFO of Lot 7. Details about the PQ-test will be issued with the Invitation to Tender.
8) The complete scope of Works is included in the (individual) lots 1, 2 and 3 (commitment to purchase by the Contracting Entity) and lot 7 (no commitment to call-off by the Contracting Entity). Lots 4 – 6 are combinations of lots 1 – 3, each comprising two lots from 1 - 3. It is clarified, that the scope of Works in the (individual) lots 1, 2 and 3 is identical to the scope of works of combination lots 4, 5 and 6 and that the scope of works will only be awarded once.
9) The Contracting Entity reserves the right to cancel the tender in case that the number of successful applications is deemed insufficient to reach an adequate level of competition.
1) In case a candidate relies on capacities, especially references, of other entities (subcontractors) to fulfill one or more selection criteria this subcontractor can be exchanged in the execution phase according to the conditions set-out in the contract, especially also fulfills the said selection criteria.
2) In case of an application of a consortium, the Contracting Entity accepts, that the Consortium partner, who fulfills the criteria for cable design and manufacture but not the criteria for installation may execute the contract without the other consortium partner or with a new consortium partner.
3) The non-confidential part of the tender package is directly available to applicants via the weblink mentioned under section I.3) of the contract notice.
4) Access to the confidential part of the tender package will be granted to the selected candidates as further set out in the invitation to tender (ITT).
5) Information to access the tender on the Ariba platform will be provided by e-mail as soon as possible. Applicants are advised to request this access as soon as possible and to click on ‘intend to participate’ in Ariba in order to receive possible clarifications from the contracting entity. The applicant must request, complete and submit by the closing date (see IV.2.2.) the selection questionnaire (SQ) with the most current available data together with the requested documents. Contracting entity doesn’t guarantee to provide the Ariba login details before closing time for candidates requesting their access to Ariba less than 48 hours before closing time.The applicant is solely responsible for requesting the access to the tender on the Ariba platform on time.The contracting entity declines any responsibility in the event of problems with the Ariba platform. Any application not sent correctly via Ariba will be rejected. The manuals for usage of E-Sourcing (Ariba) can be found via the following URL: http://www.elia.be/en/suppliers/information-and-tools-for-suppliers#ariba
6) Next to the Contracting Entities mentioned in I.1) also companies currently and in future belonging to the Elia Group may call-off the works of Lots 1 – 7. In addition, the Contracting Entity is planning to foresee in the right to interchange projects between and inside the lots according to the conditions set-up in the contract.
7) The Contracting Entity points out, that for Lots 1 – 6 a PQ-test at time of the BAFO is a mandatory condition for award. For Lot 7 a PQ-test is a mandatory condition at the time of the call-off and must therefore not yet be present at the time of the BAFO of Lot 7. Details about the PQ-test will be issued with the Invitation to Tender.
8) The complete scope of Works is included in the (individual) lots 1, 2 and 3 (commitment to purchase by the Contracting Entity) and lot 7 (no commitment to call-off by the Contracting Entity). Lots 4 – 6 are combinations of lots 1 – 3, each comprising two lots from 1 - 3. It is clarified, that the scope of Works in the (individual) lots 1, 2 and 3 is identical to the scope of works of combination lots 4, 5 and 6 and that the scope of works will only be awarded once.
9) The Contracting Entity reserves the right to cancel the tender in case that the number of successful applications is deemed insufficient to reach an adequate level of competition.
Objekt Umfang der Beschaffung
Kurze Beschreibung:
This tender contains a binding scope of seven on- and offshore connections with 525 kV HVDC power cables on basis of EPCI-contracts. The four offshore and three onshore projects are divided into three lots (1 - 3) containing an overall binding volume of 3.536 km core cable length. Additionally the contracting Entity is awarding a lot (Lot 7) with optional volume for future projects with an expected volume of 900 km core cable length and a maximum volume of 2.700 km core cable length.
This tender contains a binding scope of seven on- and offshore connections with 525 kV HVDC power cables on basis of EPCI-contracts. The four offshore and three onshore projects are divided into three lots (1 - 3) containing an overall binding volume of 3.536 km core cable length. Additionally the contracting Entity is awarding a lot (Lot 7) with optional volume for future projects with an expected volume of 900 km core cable length and a maximum volume of 2.700 km core cable length.
The complete scope of Works is included in the (individual) lots 1, 2 and 3 (commitment to purchase by the Contracting Entity) and lot 7 (no commitment to call-off by the Contracting Entity). Lots 4 – 6 are combinations of lots 1 – 3, each comprising two lots from 1 - 3. It is clarified, that the scope of Works in the (individual) lots 1, 2 and 3 is identical to the scope of works of combination lots 4, 5 and 6 and that the scope of works will only be awarded once.
The complete scope of Works is included in the (individual) lots 1, 2 and 3 (commitment to purchase by the Contracting Entity) and lot 7 (no commitment to call-off by the Contracting Entity). Lots 4 – 6 are combinations of lots 1 – 3, each comprising two lots from 1 - 3. It is clarified, that the scope of Works in the (individual) lots 1, 2 and 3 is identical to the scope of works of combination lots 4, 5 and 6 and that the scope of works will only be awarded once.
Höchstzahl der Lose pro Bieter: 2
Informationen über Lose:
In respect of lots 1-6 the bidder may bid on all lots, but may only receive one award. In respect of lot 7 no restrictions. Hence a bidder can receive a total of two awards in this tender. In case the bidder has submitted the most economic bid for several lots, the Contracting Entity will generally choose the most economic solution. Details will be provided in the Invitation to Tender. See VI.3)8)
In respect of lots 1-6 the bidder may bid on all lots, but may only receive one award. In respect of lot 7 no restrictions. Hence a bidder can receive a total of two awards in this tender. In case the bidder has submitted the most economic bid for several lots, the Contracting Entity will generally choose the most economic solution. Details will be provided in the Invitation to Tender. See VI.3)8)
Bezeichnung des Loses: Lot 1 (Project SOL+, Project OST-2-4, Project Bornholm Energy Island)
Losnummer: 1
Kurze Beschreibung:
Production, Transport and Installation of three HVDC electrical grid connection systems. The Contracting Entity is committed to call-off/purchase the projects mentioned. This lot will be awarded to maximum one bidder.
For the onshore project permanent civil works is excluded of the scope.
3. Project Bornholm Energy Island with approx. 585km (core cable lengths, 585km are only the 50Hertz share of that interconnector project) - offshore project, foreseen commissioning year: Indicative 2030
In total this lot contains approx. 1.355 km core cable length. Up to 15 % of additional volume should be considered for possible additional works.
Beschreibung der Optionen: See price sheet for details.
Bezeichnung des von der EU finanzierten Projekts oder Programms: Project Bornholm Energy Island
Bezeichnung des Loses: Lot 2 (Project NOR-11-1, Project NOL (DC31))
Losnummer: 2
Kurze Beschreibung:
Production, Transport and Installation of two HVDC electrical grid connection systems. The Contracting Entity is committed to call-off/purchase the projects mentioned. This lot will be awarded to maximum one bidder.
1. Project NOR-11-1 with approx. 636km (core cable lengths), offshore project, foreseen commissioning year 2030
2. Project NOL (DC31) with approx. 375km (core cable lengths) 375km are only the 50Hertz share of that project, onshore project foreseen commissioning year 2032
In total this lot contains approx. 1.011 km core cable length. Up to 15 % of additional volume should be considered for possible additional works.
Beschreibung der Optionen: See price sheet for details
Bezeichnung des Loses: Lot 3 (Project DC32, Project NOR-13-2)
Losnummer: 3
Kurze Beschreibung:
1. Project DC32 with approx. 375km (core cable lengths) 375km are only the 50Hertz share of that project, onshore project, foreseen commissioning year: tbd
In total this lot contains approx. 1.170 km core cable length. Up to 15 % of additional volume should be considered for possible additional works.
Bezeichnung des Loses: Lot 4 (Combined bid for Lot 1+2)
Losnummer: 4
Kurze Beschreibung: Combined bid for Lot 1+2
Bezeichnung des Loses: Lot 5 (Combined bid for Lot 1+3)
Losnummer: 5
Kurze Beschreibung: Combined bid for Lot 1+3
Bezeichnung des Loses: Lot 6 (Combined bid for Lot 2+3)
Losnummer: 6
Kurze Beschreibung: Combined bid for Lot 2+3
Bezeichnung des Loses: Lot 7 (Optional volume for future projects)
Losnummer: 7
Kurze Beschreibung:
Production, Transport and Installation of HVDC electrical grid connection systems. It can be onshore and offshore projects. For the onshore projects permanent civil works is excluded of the scope.
Expected call off volume is 900km (core cable length) and the maximum call-off volume of core cable km will be 2.700km. However, no commitment to call-off is given by Employer, This lot is only for optional volume and functions as a framework agreement.
Expected call off volume is 900km (core cable length) and the maximum call-off volume of core cable km will be 2.700km. However, no commitment to call-off is given by Employer, This lot is only for optional volume and functions as a framework agreement.
The top four bidders will be awarded with a framework agreement. The call-offs will be placed with the first-ranked bidder. In case the first ranked bidder rejects the call-off within four weeks, the call-off will be placed with the second-ranked bidder. In case the second-ranked bidder rejects the call-off within four weeks, the call-off will be placed with third-ranked bidder. In case the third-ranked bidder rejects the call-off within four weeks, the call-off will be placed with the fourth-ranked bidder unless he rejects the call-off within four weeks.
The top four bidders will be awarded with a framework agreement. The call-offs will be placed with the first-ranked bidder. In case the first ranked bidder rejects the call-off within four weeks, the call-off will be placed with the second-ranked bidder. In case the second-ranked bidder rejects the call-off within four weeks, the call-off will be placed with third-ranked bidder. In case the third-ranked bidder rejects the call-off within four weeks, the call-off will be placed with the fourth-ranked bidder unless he rejects the call-off within four weeks.
In addition to VI.3.6) in case that the optional project is an interconnector project, the calling-off party may also be the project partner according to the further conditions set-out in the contract.
Dauer: 96 Monate
Rechtliche, wirtschaftliche, finanzielle und technische Informationen Bedingungen für die Teilnahme
Wirtschaftliche und finanzielle Leistungsfähigkeit:
(a) Languages: Agreement on the principles regarding languages as described in the introduction of the selection questionnaire (SQ) (Minimum Criterion)
(b) Exclusion grounds according §§ 123, 124 GWB: Confirmation that there are no grounds for exclusion pursuant to §§ 123, 124 GWB with regard to our company and, if applicable, those from whom the suitability is borrowed. (Minimum Criterion)
(c) Code of Conduct: Confirmation of the Employer's Code of Conduct (Minimum Criterion)
(d) Minimum wages: Confirmation that paid wages are compliant with the statutory minimum wage or collectively agreed remuneration regulations are obeyed, where applicable. (Minimum Criterion)
e) Self-declaration Sanctions against Russia
In addition and for details please refer to the Document Selection Questionnaire (SQ).
Technische und berufliche Fähigkeiten:
(1) Reference for Cable Design, Engineering and Production (Minimum Criterion)
(1a) Provide a reference project showing experience of Engineering and Production for a HVDC (>= 320 kV) onshore cable for a >50 km route within the last 5 years.
(1b) Provide a reference project showing experience of Engineering and Production for a HVDC (>= 320 kV) offshore cable for a >60 km route within the last 5 years
Both references (1a) and (1b) should show information on
• Technical solutions & concepts/ cable design
• Type test process
• Manufacturing & quality measures
(2) Reference for Installation (Minimum Criterion)
(2a) Provide a reference project showing experience of Engineering, Installation, Jointing and Commissioning for a High Voltage (>150 kV) onshore cable for >50 km route within the last 5 years.
(2b) Provide a reference project showing experience of Engineering, Installation, Jointing and Commissioning for a High Voltage (>150 kV) offshore cable for >10 km nearshore & >40 km farshore methodologies incl. land transition joint and an offshore platform pull-in and termination within the last 5 years?
(2b) Provide a reference project showing experience of Engineering, Installation, Jointing and Commissioning for a High Voltage (>150 kV) offshore cable for >10 km nearshore & >40 km farshore methodologies incl. land transition joint and an offshore platform pull-in and termination within the last 5 years?
("nearshore" <10 m water depth and „farshore“ >10 m water depth)
(3) Provision of copies of certificates of the following valid ISO certified management systems (Minimum Criterion):
- ISO 9001 or equivalent
- ISO 14001 or equivalent
- VCA, OHSAS 18001 / ISO 45001 or equivalent
In addition and for more details please refer to the Document Selection Questionnaire (SQ).
Liste und kurze Beschreibung der Regeln und Kriterien:
The applicant must request, complete and submit by the closing date (see IV.2.2.) the selection questionnaire (SQ) with the most current available data together with the requested documents.
Verfahren
Rechtsgrundlage: 32014L0025
Anwendbares Vergaberecht: German Law
Zeitpunkt des Eingangs der Angebote: 18:00
Sprachen, in denen Angebote oder Teilnahmeanträge eingereicht werden können: Englisch 🗣️
1) In case a candidate relies on capacities, especially references, of other entities (subcontractors) to fulfill one or more selection criteria this subcontractor can be exchanged in the execution phase according to the conditions set-out in the contract, especially also fulfills the said selection criteria.
1) In case a candidate relies on capacities, especially references, of other entities (subcontractors) to fulfill one or more selection criteria this subcontractor can be exchanged in the execution phase according to the conditions set-out in the contract, especially also fulfills the said selection criteria.
2) In case of an application of a consortium, the Contracting Entity accepts, that the Consortium partner, who fulfills the criteria for cable design and manufacture but not the criteria for installation may execute the contract without the other consortium partner or with a new consortium partner.
2) In case of an application of a consortium, the Contracting Entity accepts, that the Consortium partner, who fulfills the criteria for cable design and manufacture but not the criteria for installation may execute the contract without the other consortium partner or with a new consortium partner.
3) The non-confidential part of the tender package is directly available to applicants via the weblink mentioned under section I.3) of the contract notice.
4) Access to the confidential part of the tender package will be granted to the selected candidates as further set out in the invitation to tender (ITT).
5) Information to access the tender on the Ariba platform will be provided by e-mail as soon as possible. Applicants are advised to request this access as soon as possible and to click on ‘intend to participate’ in Ariba in order to receive possible clarifications from the contracting entity. The applicant must request, complete and submit by the closing date (see IV.2.2.) the selection questionnaire (SQ) with the most current available data together with the requested documents. Contracting entity doesn’t guarantee to provide the Ariba login details before closing time for candidates requesting their access to Ariba less than 48 hours before closing time.The applicant is solely responsible for requesting the access to the tender on the Ariba platform on time.The contracting entity declines any responsibility in the event of problems with the Ariba platform. Any application not sent correctly via Ariba will be rejected. The manuals for usage of E-Sourcing (Ariba) can be found via the following URL: http://www.elia.be/en/suppliers/information-and-tools-for-suppliers#ariba
5) Information to access the tender on the Ariba platform will be provided by e-mail as soon as possible. Applicants are advised to request this access as soon as possible and to click on ‘intend to participate’ in Ariba in order to receive possible clarifications from the contracting entity. The applicant must request, complete and submit by the closing date (see IV.2.2.) the selection questionnaire (SQ) with the most current available data together with the requested documents. Contracting entity doesn’t guarantee to provide the Ariba login details before closing time for candidates requesting their access to Ariba less than 48 hours before closing time.The applicant is solely responsible for requesting the access to the tender on the Ariba platform on time.The contracting entity declines any responsibility in the event of problems with the Ariba platform. Any application not sent correctly via Ariba will be rejected. The manuals for usage of E-Sourcing (Ariba) can be found via the following URL: http://www.elia.be/en/suppliers/information-and-tools-for-suppliers#ariba
6) Next to the Contracting Entities mentioned in I.1) also companies currently and in future belonging to the Elia Group may call-off the works of Lots 1 – 7. In addition, the Contracting Entity is planning to foresee in the right to interchange projects between and inside the lots according to the conditions set-up in the contract.
6) Next to the Contracting Entities mentioned in I.1) also companies currently and in future belonging to the Elia Group may call-off the works of Lots 1 – 7. In addition, the Contracting Entity is planning to foresee in the right to interchange projects between and inside the lots according to the conditions set-up in the contract.
7) The Contracting Entity points out, that for Lots 1 – 6 a PQ-test at time of the BAFO is a mandatory condition for award. For Lot 7 a PQ-test is a mandatory condition at the time of the call-off and must therefore not yet be present at the time of the BAFO of Lot 7. Details about the PQ-test will be issued with the Invitation to Tender.
7) The Contracting Entity points out, that for Lots 1 – 6 a PQ-test at time of the BAFO is a mandatory condition for award. For Lot 7 a PQ-test is a mandatory condition at the time of the call-off and must therefore not yet be present at the time of the BAFO of Lot 7. Details about the PQ-test will be issued with the Invitation to Tender.
8) The complete scope of Works is included in the (individual) lots 1, 2 and 3 (commitment to purchase by the Contracting Entity) and lot 7 (no commitment to call-off by the Contracting Entity). Lots 4 – 6 are combinations of lots 1 – 3, each comprising two lots from 1 - 3. It is clarified, that the scope of Works in the (individual) lots 1, 2 and 3 is identical to the scope of works of combination lots 4, 5 and 6 and that the scope of works will only be awarded once.
8) The complete scope of Works is included in the (individual) lots 1, 2 and 3 (commitment to purchase by the Contracting Entity) and lot 7 (no commitment to call-off by the Contracting Entity). Lots 4 – 6 are combinations of lots 1 – 3, each comprising two lots from 1 - 3. It is clarified, that the scope of Works in the (individual) lots 1, 2 and 3 is identical to the scope of works of combination lots 4, 5 and 6 and that the scope of works will only be awarded once.
9) The Contracting Entity reserves the right to cancel the tender in case that the number of successful applications is deemed insufficient to reach an adequate level of competition.
Ergänzende Informationen Körper überprüfen
Name: Vergabekammer des Landes Berlin
Postort: Berlin
Postleitzahl: 10825
Land: Deutschland 🇩🇪
Informationen zu Fristen für Nachprüfungsverfahren:
Precise information on deadline(s) for review procedures:
The application for review proceedings before the public procurement tribunal is inadmissible if:
1) The applicant became aware of the claimed violation of public procurement provisions before filing the application for review, but did not complain to the contracting entity within a time limit of 10 calendar days; the expiry of the time limit under § 134 (2) GWB remains unaffected;
Informationen zu Fristen für Nachprüfungsverfahren
1) The applicant became aware of the claimed violation of public procurement provisions before filing the application for review, but did not complain to the contracting entity within a time limit of 10 calendar days; the expiry of the time limit under § 134 (2) GWB remains unaffected;
2) Violations of public procurement provisions which become apparent from the tender notice are not notified to the contracting entity by the end of the time limit for the application or the submission of a tender specified in the notice;
3) Violations of public procurement provisions which only become apparent from the procurement documents are not notified to the contracting entity by the end of the time limit for the application or the submission of a tender specified in the notice;
Informationen zu Fristen für Nachprüfungsverfahren
3) Violations of public procurement provisions which only become apparent from the procurement documents are not notified to the contracting entity by the end of the time limit for the application or the submission of a tender specified in the notice;
4) More than 15 calendar days have expired since receipt of notification from the contracting entity that it is unwilling to redress the objection.
Sentence 1 shall not apply to an application under § 135 (1) No 2 GWB to have the contract declared ineffective. § 134(1) sentence 2 GWB shall remain unaffected.
Quelle: OJS 2022/S 250-731268 (2022-12-23)
Ergänzende Angaben (2023-01-26) Objekt Metadaten der Bekanntmachung
Dokumenttyp: Ergänzende Angaben
Gemeinsames Vokabular für öffentliche Aufträge (CPV)
Code: Verlegen von Kabeln📦