2022-07-05He Dreiht - Marine Warranty Survey (MWS) (EnBW He Dreiht GmbH)
EnBW has engaged an insurance company to cover risks during transport and installation for different trades of the He Dreiht wind farm through the CAR insurance. Part of the insurance contract is the requirement of a MWS contractor to be appointed by the Client. MWS (Marine Warranty Surveyor) means the inspectors to be engaged by the Contractor.
For the MWS service, the Scope of Work will be splitted into following sub-trades:
1. Wind Turbine Generator (WTG)
2. Foundation (FOU)
3. Inner Array Grid (IAG)
Ansicht der Beschaffung » Erwähnte Lieferanten:Con4Mare GmbH & Cie. KGGermanischer Lloyd Industrial Services GmbH
2018-05-29Acquise von gesicherte(n) Fläche(n) zur Errichtung von Windenergieanlagen (Onshore) inklusive der Projektentwicklung... (EnBW AG)
Sie bieten aus Ihrem Portfolio eine gesicherte Fläche(n) zur Errichtung von Windenergieanlagen (Onshore) inklusive der Projektentwicklung durch Ihr Unternehmen (Standorte innerhalb der Bundesrepublik Deutschland) der EnBW zum Erwerb an.
Voraussetzung für die Qualifikation Ihres Windenergieanlagenstandortes/Projektes ist, dass es.
a) mit wenigstens schuldrechtlich gesicherten Grundstücksrechten (branchenübliche Pacht-/Nutzungsverträge) ausgestattet ist.
b) sich auf dem Territorium der Bundesrepublik …
Ansicht der Beschaffung »
2016-02-09Lieferung und Errichtung von bis zu neun Windenergieanlagen im Stadtgebiet Münster (Stadtwerke Münster GmbH)
Die Beschaffung beinhaltet die Herstellung, den Transport, die Errichtung, Inbetriebnahme und den Probebetrieb von bis zu neun Windenergieanlagen im Stadtgebiet Münster. Optional werden ebenfalls Wartungsleistungen mit angefragt. Folgende Einschränkungen bzw. Mindestforderungen sind zu
beachten:
— Die Windenergieanlagen müssen eine Nennleistung von 2,0 MW bis 3,5 MW haben,
— Die zulässige Gesamthöhe ist 150 Meter (6-8 Anlagen) bzw. 180 Meter (1-3 Anlagen),
— Der Rotordurchmesser muss mindestens 100 Meter …
Ansicht der Beschaffung »
2015-08-14Subject of the contracts is the design, manufacture, supply, installation and maintenance of Wind Turbine Generators... (Trianel GmbH)
Design, manufacture, supply, storage, delivery, transport (on- and offshore), including provision of necessary logistics on- and offshore including installation vessel, installation (including installation engineering and supply of sea fastenings and grillages), assembly, commissioning, termination, test operation, documentation, service and maintenance of WTG and towers with a minimum capacity of 6 MW each (including guaranteed availability of the WTG's). A Project Summary which can be requested form …
Ansicht der Beschaffung » Erwähnte Lieferanten:Senvion GmbH
2014-07-21Offshore Windpark (OWP) EnBW Hohe See – Los Windturbine mit Gründungsstruktur (WTG/FOU) (EnBW Energie Baden Württemberg AG)
Planung, Herstellung, Lieferung, Transport, Installation, Inbetriebnahme, Probebetrieb und Dokumentation für bis zu 80 Windturbinen mit Gründungsstrukturen (auf dem bestehenden Windparklayout Hohe See) incl. Windpark SCADA und Windturbinen-Servicevertrag. Windturbinentyp zwischen 3,6 MW und der 6-MW Klasse.
Die finale Auftragsvergabe ist u. a. abhängig von gesetzlichen Rahmenbedingungen, Genehmigungen und der Netzanbindung. Der Vertragsabschluss ist für 2015 vorgesehen. Die Fertigstellung soll bis …
Ansicht der Beschaffung »
2014-04-10EPCI & SMA Wind Turbine Generators (Nordsee One GmbH)
Design, certify, supply, installation, commission and test (full EPCI) of 54 WTGs (rotor-nacelle-tower-assembly) with a nominal power from 5.0 MW up to 6.15 MW, rotor diameter 126 m up to 154 m, 54 x Towers (Tower starting from interface level with transition piece) 54 x Medium voltage switchgears, 54 x Platform Cranes, 1 x SCADA System incl. Park Controller.
EPCI to include: design of the foundation and substructure for the WTG. The design shall include the certifiable basic and detail design of both …
Ansicht der Beschaffung » Erwähnte Lieferanten:Senvion SE
2013-11-08Turbine supply agreement for Duben (Vattenfall Europe Windkraft GmbH)
The whole project consists of 9 to 11 Wind Turbine Generators (WTGs) incl. foundations, the necessary roads and hardstands, the cables incl. design, manufacturing and installation, as well as the substation, the fiber design, manufacturing and installation. Nine Wind Turbines will be located on a field, two Wind Turbines in a small forest area. The wind farm is located 93 km away from Berlin. The whole site area is 420 ha.
This contract includes all required work for the supply of 9 to 11 Wind Turbine …
Ansicht der Beschaffung »
2013-07-23Bau von Onshore Windenergieanlagen an verschiedenen Standorten in Süd-Deutschland (ZEAG Erneuerbare Energien GmbH)
Herstellung, Umsetzungsplanung, Lieferung, Installation, Inbetriebnahme, Probebetrieb, Abnahme, Dokumentation und Service/Vollwartung (5–20 Jahren) von ca. 6 Windparkprojekte und ca. 80 Onshore-Windenergieanlagen an verschiedenen Standorten in Süd-Deutschland mit Baurealisierungszeitraum 2015-16. Der Auftragsumfang erweitert sich um den Fundamentbau, wenn hierfür technische oder rechtliche Gründe des Lieferanten gegeben sind. Ansonsten kann der Fundamentbau als Option angeboten werden. Der Auftraggeber …
Ansicht der Beschaffung »
2013-02-14Lieferung und Errichtung von drei Windenergieanlagen im Stadtgebiet Münster (Stadtwerke Münster GmbH)
Die Beschaffung beinhaltet die Herstellung, den Transport, die Errichtung, Inbetriebnahme und den Probebetrieb von drei Windenergieanlagen im Stadtgebiet Münster. Optional werden ebenfalls Wartungsleistungen mit angefragt. Folgende Einschränkungen bzw. Mindestforderungen sind zu beachten:
— Die Windenergieanlagen müssen mindestens eine Nennleistung von 2,0 MW haben;
— Die zulässige Gesamthöhe ist 150 Meter;
— Der Rotordurchmesser muss mindestens 100 Meter betragen;
— Es muss möglich sein, die …
Ansicht der Beschaffung » Erwähnte Lieferanten:Nordex Energy GmbH
2012-10-19Lieferung einer MW Windenergieanlage als Testträger zu Zwecken von Forschung und Entwicklung (Deutsches Zentrum für Luft- und Raumfahrt DLR e.V.)
Für das Forschungsprojekt „DLR Forschungsplattform Windenergie“ ist die Beschaffung einer Windkraftanlage in der Größenordnung von 2,5 MW geplant, die als Testträger und zur Validierung von Forschungsergebnissen dienen soll. Der Auftrag umfasst sowohl die Lieferung und Montage der Anlage bis spätestens 2014, als auch notwendige technische Änderungen, um Forschungsaktivitäten durchführen zu können. Diese müssen in einem gemeinsamen Forschungsprojekt mit dem DLR durchgeführt werden. Zukünftig und …
Ansicht der Beschaffung »
2011-09-02Wind turbine generators (RWE Innogy Nordsee 1 GmbH)
Design, production, installation and commissioning of 54 standard wind turbine generators fo the 6 MW class and its associated three blade systems and steel towers with a hub height of approx. 100 meters LAT of the entire wind turbine generator. An operation and maintenance agreement with a term of optionally 5 or 10 years is required.