Beschaffungen: Onshore- und Offshore-Dienste (seite 3)
2015-11-19Balance of Plant — Structural (Nordsee One GmbH)
Provision of maintenance and inspections of all structural works on the offshore substation, its jacket foundation, and the wind turbine generators' monopile foundations in offshore wind farm Nordsee One. The initial contract period shall be five years, commencing 01.11.2017. Earlier commencement (01.11.2016) and extension for another five years term are optional. The Structural Services will include the provision of all required tools, equipment and personnel with the required qualifications. Onshore …
Ansicht der Beschaffung » Erwähnte Lieferanten:Semco Maritime
2015-10-19Provision of Client Representatives and Quality Inspectors for wind turbine pre-assembly, installation and... (Sandbank Offshore Wind GmbH)
The contract shall comprise the provision of specialists for quality control and site representation on behalf of the Client (SBOW) for wind turbine pre-assembly (Lot 1), for wind turbine installation (Lot 2) and for wind turbine completion and commissioning works (Lot 3). The specialists shall be required to act as Client Representatives (Reps.) and quality inspectors and ensure that the wind turbine contractor fulfils its obligations with respect to the applicable standards, contractual requirements as …
Ansicht der Beschaffung »
2015-05-01Durchführung von geophysikalischen Bohrlochmessungen im open hole und cased hole in 2 Tiefbohrungen einer... (Geothermie Holzkirchen GmbH)
Durchführung von geophysikalischen Bohrlochmessungen im open hole und cased hole in 2 abgelenkten geothermischen Tiefbohrungen (je ca. 5 500 m MD) zur Erschließung von Erdwärme am Standort Holzkirchen. Es werden Lose gebildet:
Los 1 für wireline-Messungen im open hole (23“, 16“ und 8.1/2“) und cased hole (13.3/8“, 9.5/8“/9.7/8“ und 7“) bis ca. 4 700 m MD,
Los 2 für geophysikalische Bohrlochmessungen am Strang im open hole der Malm-Sektion (6.1/8“, bis ca. 5 500 m MD),
Los 3 für wireline-Messungen im …
Ansicht der Beschaffung »
2015-04-24Übernahme der Service-Generalunternehmerschaft im Rahmen der Niederbringung einer geothermischen Dublette am... (ÜWGeo GmbH)
Übernahme der Service-Generalunternehmerschaft im Rahmen der Niederbringung von 2 abgelenkten geothermischen Tiefbohrungen zur Erschließung von Erdwärme am Standort Trebur inkl. Koordination der folgend genannten Leistungen: Richtbohrservice, Spülungsservice und Feststoffkontrolle, Zementationsservice und geophysikalische Bohrlochmessungen. Im Rahmen der Service-Generalunternehmerschaft sind auch vorbereitende und bohrungsbegleitende Aufgaben und die terminliche Koordinierung der genannten Gewerke bei …
Ansicht der Beschaffung » Erwähnte Lieferanten:Schlumberger GmbH
2015-01-20DanTysk paint repair works (DanTysk Offshore Wind GmbH)
The scope of work on this project is to clean, blast, sandpapering (manual surface preparation), and paint all the damaged areas on each of the foundation structures (TP's) and deliver the needed consumables, Paint Sandpaper etc.
It is essential that the paint repair work is carried out in accordance with Application Repair Procedure Smoulders for DanTysk Offshore Wind Farm and, NORSOK M 501 as well as the guidelines described in the paints technical data sheet.
Ansicht der Beschaffung »
2015-01-14Maritime Beratung und Unterstützung für Projekte auf offener See (TenneT Offshore GmbH)
Erbringung maritimer Beratungs- und Unterstützungsleistungen für Projekte auf offener See. Die angefragten
Leistungen beinhaltet die Funktion des Aufsicht führenden Kundenvertreters für maritime Bauprojekte (primär
Seekabelverlegung).
Der Aufsicht führende Kundenvertreter überwacht und beobachtet im Namen des Auftraggebers die durch einen
Generalunternehmer oder dessen Nachunternehmer durchgeführten Baumaßnahem auf offener See. Einsatzort
hierfür kann primär ein Schiff (z.B. eine Kabelverlegeeinheit) …
Ansicht der Beschaffung »
2015-01-05Sandbank — Marine Coordination Function (Sandbank Offshore Wind GmbH)
The contract shall comprise the provision of personnel to perform the ‘Marine Coordination’ function for the construction phase of the Sandbank Offshore Wind Farm (SBOW). ‘Marine Coordination’ will oversee all marine operations in the wind farm, provide advice to vessel Masters and coordinate an emergency response to any incident within the wind farm. The task encompasses traffic control for all vessels at the Offshore Installation Site, as well as people and equipment tracking.
Marine Coordination must …
Ansicht der Beschaffung »
2014-12-03DanTysk steel structures with exception of WTG towers inspection, maintenance and repairs (DanTysk Offshore Wind GmbH)
The contract shall comprise the inspection, maintenance and repair services for the steel structures of the DanTysk wind farm. The scope of work shall cover the planning, managing and performance of the structural above water level inspection, maintenance and repair services for eighty (80) wind turbine generator (WTG) foundations, one (1) offshore substation (OSS) jacket foundation and topside as well as one (1) offshore accommodation platform (OAP) jacket and topside. The scope of work shall include …
Ansicht der Beschaffung »
2014-09-18Maritime Unterstützung für Netzanschlusssysteme auf See der TenneT einschließlich ihrer Beteiligungsgesellschaften (TenneT Offshore GmbH)
Erbringung maritimer Unterstützungsleistungen für Projekte auf offener See. Die angefragten Leistungen sind in vier Lose aufgeteilt, die die Funktionen:
— der Gestellung von Guard Vessels Klasse A und B (Los 1),
— der Gestellung von Guard Vessels Klasse C (Los 2),
— der Gestellung von Crew Transfer Vessels (Los 3),
— der Gestellung von Emergency Response and Rescue Vessels (Los 4) beinhalten.
Grundsätzlich können sich interessierte Unternehmen für 1, 2, 3 oder alle 4 Lose in freier Kombination bewerben.
Ansicht der Beschaffung »
2014-02-26Logging für Appraisal Well Reudnitz E Rdn 2/14 der Bayerngas GmbH (Bayerngas GmbH)
Die Ausschreibung erfolgt gem. § 129b GWB
Die Bayerngas GmbH ist Inhaberin einer Erlaubnis zur Aufsuchung von bergfreien Bodenschätzen, nämlich von Kohlenwasserstoffen nebst den bei ihrer Gewinnung anfallenden Gasen im Feld Reudnitz. Für das Quartal Q2 2014 ist eine Aufsuchungsbohrung zur Erkundung einer Erdgaslagerstätte im Rotliegend in einer Teufe von ca. 2 730 m geplant. Im Anschluss an die Vertikalbohrung ist ein Sidetrack mit einer Horizontalstrecke bis zu 1 000 m geplant. Durch umfangreiche …
Ansicht der Beschaffung »
2013-09-25Service Base for Offshore Windfarm Nordsee One (Nordsee One GmbH)
The contract to be awarded concerns the services regarding the provision of onshore facilities and 2 berths for 2 crew transfer vessel for N1. The onshore facilities should consist of an administration area, social rooms, a kitchen, sanitary facilities, a heated room and ventilated (for drying clothes and lifesaving equipment), a storage area with suitable environmental conditions, workshop room, electrical storage area, hazardous material area as well as a waste and disposal area required for the …
Ansicht der Beschaffung » Erwähnte Lieferanten:Norddeicher Schiffswerft GmbH
2013-07-23Bau von Onshore Windenergieanlagen an verschiedenen Standorten in Süd-Deutschland (ZEAG Erneuerbare Energien GmbH)
Herstellung, Umsetzungsplanung, Lieferung, Installation, Inbetriebnahme, Probebetrieb, Abnahme, Dokumentation und Service/Vollwartung (5–20 Jahren) von ca. 6 Windparkprojekte und ca. 80 Onshore-Windenergieanlagen an verschiedenen Standorten in Süd-Deutschland mit Baurealisierungszeitraum 2015-16. Der Auftragsumfang erweitert sich um den Fundamentbau, wenn hierfür technische oder rechtliche Gründe des Lieferanten gegeben sind. Ansonsten kann der Fundamentbau als Option angeboten werden. Der Auftraggeber …
Ansicht der Beschaffung »
2013-02-08CIV 2: Marine Construction of WTG Foundations Package (Sandbank Offshore Wind GmbH)
The whole project consists of 96 WTGs, WTG Foundations, Inter Array Cables and an Offshore Substation (OSS). The wind farm is located in the German Bight, 90 km west of the island of Sylt, in the German Exclusive Economic Zone (EEZ). The location provides water depths between 25 and 34 meters. The Sandbank project is equipped with an irrevocable permit. In a first construction phase 288 MW will be realized.
The scope of work of this tender includes marine construction, installation, transportation …
Ansicht der Beschaffung »
2012-11-08Design, engineering, supply, construction, installation and commissioning of an offshore substation (OSS) (Sandbank Offshore Wind GmbH)
The whole project consists of 96 WTGs, WTG foundations, Inter Aray cables and an Offshore Substation (OSS). The windfarm is located in the German Bight, 90 km west of the island of Sylt, in the German Exclusive Economic Zone (EEZ). The location provides water depths between 25 and 34 meters. The Sandbank project is equipped with an irrevocable permit. In a first construction phase 288 MW will be realised.
The scope of work of this tender includes the design, engineering, supply, construction, …
Ansicht der Beschaffung »
2012-03-12Kabellage- und hydrographische Vermessungen an den in Betrieb befindlichen Seekabeln der Projekte alpha ventus und BorWin1 (TenneT Offshore GmbH)
— Erstellung/Einreichung von Verfahrensbeschreibungen/-anweisungen bzgl. der durchzuführenden Untersuchungen,
— Erkundungen inklusive Mobilisierung und Demobilisierung,
— Durchführung von zerstörungsfreien Messungen (ca. 180 km Trassenverlauf, ggf. z.T. ohne Eigensignalausstrahlung) zur Bestimmung der Eingrabetiefe entlang der Trassenverläufe in Wassertiefen zwichen ca. 0 m - 40 m,
— Datenerhebung bzgl. Bathymetrie mittels Fächerecholot sowie Abbildung des Meeresbodens mittels Seitensichtsonar,
— …
Ansicht der Beschaffung »
2012-02-29Rahmenvertrag für Geophysikalische und Geotechnische Erkundungen entlang von Trassenverläufen (TenneT Offshore GmbH)
Nachfolgende Tätigkeiten sind dabei im Zuge der Leistungserbringung durchzuführen:
— Erstellung/Einreichung von Verfahrensanweisungen und Plänen bzgl. Trassenuntersuchungen,
— Trassenuntersuchungen bzgl. Bathymetrie, Geophysik, Geotechnik und Geologie,
— Flugzeuggestützte LIDAR und -magnetikmessungen,
— Lagesbestimmungen vorhandener Kabel und Rohrfernleitungen,
— Trassenuntersuchung geologischer Lagerungsbedingungen und geologischer Charakteristiken des Meeresgrundes,
— Kartierung von Hindernissen wie …
Ansicht der Beschaffung »
2012-02-09Offshore-Catering und Room-Service (Global Tech I Offshore Wind GmbH)
Der Auftrag umfasst das Catering einschließlich Reinigungs- und Wäschereidienstleistungen (Room-Service) für die bemannte Umspannstation des Offshore-Windparks "Global Tech I" in der Deutschen Nordsee. Das Projektgebiet "Global Tech I" hat die Eckkoordinaten (geografisches Bezugssystem WGS 84):
006°23.320'E 54°27,236'N.
006°19,008'E54°29,940'N.
006°19,090'E54°32,452'N.
006°24,949''E54°32,450'N.
Und liegt in der Deutschen Ausschließlichen Wirtschaftszone. Die Basisstation auf dem Festland wird in …
Ansicht der Beschaffung » Erwähnte Lieferanten:F.O.S.S. & E.S.G. Catering Ltd.
2011-11-14Offshore Trassenuntersuchung für den Netzanschluss von Offshore-Windparks (TenneT Offshore GmbH)
Offshore-Trassenuntersuchung (Korridorbreite bis zu 2 km, Wassertiefe hauptsächlich zwischen 0 m und 25 m im Trassenverlauf).
— Erstellung/Einreichung von Verfahrensanweisungen bzgl. der Trassenuntersuchung,
— Trassenuntersuchung inkl. Mob/Demob,
— Datenerhebung bzgl. Bathymetrie, Morphologie und Geologie,
— Lagebestimmung vorhandener Kabel und Rohrfernleitungen,
— Trassenuntersuchung der geologischen Lagerungsbedingungen und der geologischen Charakteristik des Meeresgrundes,
— Kartierung von …
Ansicht der Beschaffung »
2011-09-02Projektabwicklungsunterstützung des Projektes Plattform für ein Offshore Netzanschlussprojekt (TenneT Offshore GmbH)
Beauftragung eines erfahrenen Unternehmens für die Projektunterstützung im Projekt Offshore Plattform, innerhalb eines Netzanschlussprojektes, für die gesamte Projektlaufzeit in Form eines Rahmenkontraktes.
Dabei sind insbesondere folgende Phasen zu berücksichtigen:
— Planungsphase,
— Bauphase inklusive aller damit verbundenen, zu installierenden technischen Anlagen,
— Verschiffungsphase der Plattform zu ihrem finalen Standort in der deutschen Nordsee,
— Errichtungsphase für die Plattform an ihrem …
Ansicht der Beschaffung »
2011-08-18Baugrunduntersuchung für Offshore-Plattform Standort(e) (TenneT Offshore GmbH)
Das Erkundungsprogramm umfasst u.a. die Untersuchung der Baugrundverhältnisse an einem oder mehreren Standorten in der Deutschen Bucht mit Wassertiefen von etwa 20 bis ca. 40 m. Gemäß eines vorliegenden Gründungskonzepts, das durch den Auftraggeber gestellt wird, soll der Baugrund an dem(n) Standort(en) hinsichtlich verschiedener Plattformgründungsvarianten (u.a. Pfahlgründung, Flachgründung) untersucht werden. Im Rahmen des Erkundungsprogramms (Geophysik und Geotechnik) können u.a. Vibrocores, Bohrungen …
Ansicht der Beschaffung »
2011-03-28Baugrunduntersuchungen für Offshore-Plattform Standorte (TenneT Offshore GmbH)
Das Erkundungsprogramm umfasst u.a. die Untersuchung der Baugrundverhältnisse an mehreren Standorten in der Deutschen Bucht mit Wassertiefen von etwa 20 bis 40 m. Gemäß eines vorliegenden Gründungskonzepts, das durch den Auftraggeber gestellt wird, soll der Baugrund an den Standorten hinsichtlich verschiedener Plattformgründungsvarianten (u.a. Pfahlgründung, Flachgründung) untersucht werden. An mehreren Standorten werden hierbei Baufelder für jeweils eine oder mehrere Plattformgründungen untersucht. Im …
Ansicht der Beschaffung »
2011-03-16Services for the project handling of an offshore-converter-platform (TenneT Offshore GmbH)
The services that have to be provided are the support of the principal during each phase of the complete project.
Namely these are: planning phase (in particular the checking of the considerable design-documents), the construction- and equipping phase of the platform incl. all related technical assets, the transportation to the final destination in the North Sea, the errection at its destination, the bringing into service as well as acceptance procedures.
In the course of the project handling, in …
Ansicht der Beschaffung »
2011-02-10Offshore-Trassenuntersuchung für den Netzanschluss von Offshore-Windparks (Offshore-Trassenuntersuchung für den Netzanschluss von Offshore-Windparks)
Offshore-Trassenuntersuchung (Korridorbreite zwischen 0,3 und 1 km, Wassertiefe hauptsächlich zwischen 20 m und 40 m im Trassenverlauf).
— Erstellung / Einreichung von Verfahrensanweisungen bzgl. der Trassenuntersuchung,
— Trassenuntersuchung inkl. Mob / Demob,
— Datenerhebung bzgl. Wassertiefe, Bathymetrie, Morphologie und Geologie,
— exakte Positionsbestimmung vorhandener Kabel und Rohrfernleitungen,
— Trassenuntersuchung bezüglich des Sedimentaufbaus,
— Trassenuntersuchung der geologischen …
Ansicht der Beschaffung »