2020-09-04Maritime Underwater Surveys with Regard to Fixed Steel Structures (Offshore Platforms) (TenneT Offshore GmbH)
The client manages the operations of the German and Dutch high voltage cable connections from land to the offshore wind farms, so-called grid connection systems (GCS). Adequate maintenance to the fixed steel offshore structures must be ensured. The underwater inspections of the fixed steel structures form an integral part of the maintenance and the source of information on which maintenance is scheduled.
Besides these scheduled surveys that are part of the maintenance plans, the surveys are also needed …
Ansicht der Beschaffung »
2020-08-26Korrosionsschutzleistungen (OSS) (Global Tech I Offshore Wind GmbH)
Gegenstand des Vergabeverfahrens sind Reparaturleistungen an der Korrosionsschutzbeschichtung am Umspannwerk (OSS) des Offshore Windparks Global Tech I (GTI).
Die Errichtung des Windparks GTI, der aus achtzig 5-MW-Offshore-Windturbinen und der OSS besteht, wurde 2014 abgeschlossen. Der Windpark befindet sich etwa 110 km nördlich von Cuxhaven in der deutschen Ausschließlichen Wirtschaftszone (AWZ) der Nordsee. Die mittig im Windpark befindliche OSS wurde bereits im Mai 2013 errichtet. Die Abmessungen der …
Ansicht der Beschaffung »
2020-07-21Betrieb der Forschungsplattform FINO2 (Bundesministerium für Wirtschaft und Energie (BMWi))
Der Betrieb der „Forschungsplattformen in Nord- und Ostsee“ (FINO) dient der grundlegenden Daten- und Erkenntnisgewinnung für die Offshore-Windenergienutzung. Die Projekte umfassen alle Bereiche der Maritimen Forschung.
Das BMWi beabsichtigt, den Betrieb der FINO2 bis zum 28.2.2025 mit optionaler einjähriger Verlängerung in Auftrag zu geben.
Zu den Kernaufgaben des Betreibers gehören u. a. die planmäßige Wartung und Instandsetzung, Organisation des Forschungsbetriebes in Abstimmung mit den …
Ansicht der Beschaffung » Erwähnte Lieferanten:GL Garrad Hassan Deutschland GmbH
2020-06-08Marine, Flight and Emergency Response Coordination Services (Trianel Windkraftwerk Borkum GmbH & Co. KG)
Service of execution of marine, flight and emergency response coordination service for the TWBI offshore windfarm, phase 1 and IWB offshore substation including the provision of personnel, equipment, software, establishment of interfaces to OWF [offshore windfarm] data/information as well as the preparation of any necessary documentation.
TWBI: Execution of marine, flight and emergency response coordination service, operations monitoring and control of TWBIs offshore windfarm.
IWB: Execution of marine, …
Ansicht der Beschaffung »
2020-03-12Betrieb der Forschungsplattform FINO 2 (Bundesministerium für Wirtschaft und Energie (BMWi))
Der Betrieb der „Forschungsplattformen in Nord- und Ostsee“ (FINO) dient der grundlegenden Daten- und Erkenntnisgewinnung für die Offshore-Windenergienutzung. Die Projekte umfassen alle Bereiche der Maritimen Forschung.
Das BMWi beabsichtigt, den Betrieb der FINO2 bis zum 31.8.2024 mit optionaler einjähriger Verlängerung in Auftrag zu geben.
Zu den Kernaufgaben des Betreibers gehören u. a. die planmäßige Wartung und Instandsetzung, Organisation des Forschungsbetriebes in Abstimmung mit den …
Ansicht der Beschaffung »
2020-02-09Construction of AC Grid Connection Systems for Projects Kaskasi II and Gode Wind 3: (TenneT Offshore GmbH)
Turnkey construction of 2 AC grid connection systems to connect the offshore wind farms Kaskasi II (approx. 342 MW) and Gode Wind 3 (approx. 242 MW) to the associated HVDC sea stations. The scope comprises all works from design to manufacturing, delivery and installation up to operational commissioning of a secure and high availability transmission of electrical energy from the grid connection points at the HVDC offshore station to the AC grid connection points on the OWF (Offshore Wind Farm) station. …
Ansicht der Beschaffung »
2019-11-22Nordsee One GmbH — SMA WTGs (Nordsee One GmbH)
The wind farm Nordsee One (N1) is located in the German Bight, approximately 32 km north of the island Juist. The water depth ranges roughly between 26 m and 34 m (LAT) with 2,7 m tidal range. Under operation are 54 Senvion wind turbine generators (WTG) of 6.2M126 type with a nominal output of 6.15 MW.
N1 wants to enter into a Service- and maintenance agreement (SMA) with a long-term full-scope service for the 54 WTGs, starting from 7.12.2020 until 6.12.2027. The main tasks of the scope will be …
Ansicht der Beschaffung »
2019-10-02Provision of a Platform Supply Vessel (Tennet TSO GmbH)
TenneT is looking for reliable, trustworthy and highly professional providers of DP2-compliant Platform Supply Vessels (PSV) to conclude a contract for the duration of 3 years plus extensions for regular cargo transports to and from the offshore platforms in the German and Dutch North Sea.
Ansicht der Beschaffung »
2019-08-26Betrieb der Forschungsplattform FINO 1 (Bundesministerium für Wirtschaft und Energie (BMWi))
Im Zuge der Planung und des Ausbaus von Anlagen zur Erzeugung von elektr. Strom aus erneuerbaren Energien wurde mit den Projekten „Forschungsplattformen in Nord- und Ostsee“ (FINO) die Grundlage für die erfolgreiche Planung und Umsetzung von Offshore-Windparks geschaffen. Das BMWi beabsichtigt, den Betrieb der FINO1 bis zum 31.7.2023 mit optionaler einjähriger Verlängerung zu vergeben.
Zu den Kernaufgaben des Betreibers gehören die planmäßige Wartung und Instandsetzung, Organisation des …
Ansicht der Beschaffung » Erwähnte Lieferanten:Forschungs- und Entwicklungszentrum...
2019-02-09Provision of Emergency Response and Rescue Vessels and Guard Vessels (TenneT Offshore GmbH)
TenneT is looking for providers of ERRVs and guard vessels to conclude contracts for the duration of 3 years per lot with possibilities to twice extend the duration by another year. The tender is separated into 2 lots (per vessel type).
Lot 1 covers to provision of Emergency Response and Rescue Vessels (ERRV) and crews to ensure safety of people working offshore over the side or underneath the platforms. Main duties are to cover overboard works and rescue persons from the water and providing them with …
Ansicht der Beschaffung » Erwähnte Lieferanten:Rederij Groen III BV
2019-01-29Stimulationsarbeiten an einer Bohrung in Ungarn (Helmholtz-Zentrum Potsdam, Deutsches GeoForschungsZentrum GFZ – Einkauf)
Das Deutsche GeoForschungsZentrum GFZ erforscht im Rahmen des Demonstrationsprojekt DESTRESS sanfte Stimulationsmethoden in Geothermiereservoiren. Am Standort Mezöbereny in Ungarn soll durch chemische Stimulation die Injektivität einer Bohrung erhöht werden. Die Stimulation besteht aus drei Schritten, einer Bestandsaufnahme durch Logging und hydraulische Tests, der Stimulation und der Nachuntersuchung (Logging und hydraulische Tests) zur Validierung der Injektivitätserhöhung.
Ansicht der Beschaffung »
2018-12-13Client Representatives for Maritime Consultancy and Services (TenneT Offshore GmbH)
Provision of maritime consultancy and services for offshore projects, operations and maintenance campaigns. The inquired service contains the function of the client representative on site for operations and maintenance campaigns (primarily offshore surveys) = lot 1 as well as maritime projects (primarily offshore cable installations) = lot 2.
The client representative monitors and observes the offshore works performed by the contractor respectively his subcontractors being contracted.
Place of action is …
Ansicht der Beschaffung » Erwähnte Lieferanten:Atlas Services Group BVeos projekt GmbHMetoc Ltd
2018-11-20Trassensicherung – Fischereikoordination CWA 2.0 (50Hertz Offshore GmbH)
Der Umfang der zu erbringenden Dienstleistungen umfasst die Fischereikoordination zur Trassensicherung, d. h. das Freihalten der Arbeitsbereiche von Fischereitätigkeiten und deren Equipment (z. B. Netze, Reusen etc.) sowie die Abstimmung der Projektarbeiten mit den lokalen maritimen Unternehmen, Genossenschaften und Fischereiaufsichtsstationen.
Ansicht der Beschaffung »
2018-08-30Schiffsdienstleistungen für den Transport von Offshore Containern inklusive Gefahrgut, Stückgut und Betankung für... (Gobal Tech I Offshore Wind GmbH)
Die Errichtung der Offshore-Windparks GTI und BO1 in der deutschen ausschließlichen Wirtschaftszone der Nordsee ist abgeschlossen. Die Auftraggeber beabsichtigen, für den regelmäßigen Transport von Containern inklusive Gefahrgut, Stückgut und/oder Betankung der Substation von Emden zum Windpark und zurück einen Dienstleister mit der Durchführung von Schiffsdienstleistungen der Offshore Versorgung zu beauftragen.
Es soll alle 2 bis 4 Wochen eine Einzelfahrt zu einem dieser Offshore-Windparks oder eine …
Ansicht der Beschaffung »
2018-05-31CWA2 Steinräumung Ostwind 2 entlang von Seekabeltrassen zur Netzanbindung von geplanten Offshore-Windparks (OWP) von... (50Hertz Transmission GmbH)
Inhalt dieser Veröffentlichung je Los ist die fachgerechte, genehmigungskonforme und dem aktuellen Stand der Technik entsprechende Räumung von Steinen auf den Kabeltrassen OST-2-1, OST-2-2 und OST-2-3.
Zur Gewährleistung einer genehmigungskonformen Kabellegung sind alle sichtbaren oder teilweise vorstehenden Steine mit einem Durchmesser ≥50 cm auf einer Korridorbreite von 12 m zu beseitigen, bzw. 15 m bei Wassertiefen größer 20 m.. Vollflächig verdeckte Steine deren Oberkannte mehr als 15 cm unterhalb …
Ansicht der Beschaffung »
2018-05-29Marine Coordination (Vattenfall AB)
Marine Coordination, all Information can be found here:
https://portal.commerce-hub.com/index.cfm?action=sourcing:__requestform.subscribe&document=F3587A0F-E7E9-37FE-A21FA524084C248B
Ansicht der Beschaffung »
2018-05-092D seismische Messungen (Friedrich-Alexander Universität Erlangen-Nürnberg)
Das Geo Zentrum Nordbayern, eine Forschungseinrichtung der Friedrich-Alexander Universität Erlangen-Nürnberg (FAU) plant die Durchführung 2D seismischer Messungen im Raum Coburg – Hassfurt – Bamberg – Bayreuth und lädt Anbieter zur Abgabe von Angeboten ein. Die Messungen sind teil eines Forschungsprojektes zur Untersuchung einer geothermischen Anomalie in dieser Region. Sie sollen den Aufbau des Untergrundes und den Verlauf von Störungszonen erkunden.
Ansicht der Beschaffung »
2017-10-17Projekt CWA 2 – Marine-Koordinierungs-Service (50Hertz Offshore GmbH)
Diese Beschaffung bezieht sich auf den Marine-Koordinierungs-Service für die gesamte Dauer des 50Hertz Offshore-Projektes „Cluster Westlich Adlergrund 2“ (CWA 2) in der Ostsee, um die effektive Koordination aller Schiffe im 50Hertz Baufeld zu unterstützen. Darüber hinaus ist die effektive Koordination mit Baufeldern Dritter sowie anderer Offshore-Aktivitäten in der näheren Umgebung sicherzustellen.
Ansicht der Beschaffung »
2016-12-22Sandbank site paint repair works (Vattenfall Europe Windkraft GmbH)
The scope of work on this project is to clean, roughen, chamfer (manual surface preparation) and paint all damaged areas on each of the foundation structures (TPs) and the Offshore Substation (OSS) as well as the roughly more than 160 items in total, renovation of three warning stickers on each TP next to the boat landing ladder (no anchoring, danger of falling, keep away) and replacing the warning stickers for the ICCP anodes near the boat landings. The scope can be extended to cover any remaining paint …
Ansicht der Beschaffung »
2015-11-19Balance of Plant — Subsea (Nordsee One GmbH)
The contract to be awarded concerns the provision of maintenance and inspections of all Subsea systems and equipment for an initial period of five years, commencing 1.4.2017. Earlier commencement (1.11.2016) and extension for a further term of 5 years are optional. The Subsea Services will include the provision of all required tools, equipment and personnel with the required qualifications. Onshore facilities and access logistics (i.e. crew vessel) will be provided by the contracting entity in / out off …
Ansicht der Beschaffung » Erwähnte Lieferanten:NDE Offshore A/B
2015-11-19Balance of Plant — LV / Auxiliary (Nordsee One GmbH)
The contract to be awarded concerns the provision of maintenance and inspections of the LV and Auxiliary equipment on the offshore substation (OSS) for an initial period of five years, commencing 1.11.2017. Earlier commencement (1.11.2016) and extension for a further term of five years are optional. The LV/Auxiliary Services will include the provision of all required tools, equipment and personnel with the required qualifications. Onshore facilities and access logistics (i.e. crew vessel) will be …
Ansicht der Beschaffung » Erwähnte Lieferanten:Semco Maritime
2015-11-19Balance of Plant — HV / MV (Nordsee One GmbH)
The contract to be awarded concerns the provision of maintenance and inspections of the HV and MV equipment on the offshore substation (OSS) for an initial period of five years, commencing 1.11.2017. Earlier commencement (1.11.2016) and extension for a further term of five years are optional. The HV/MV Services will include the provision of all required tools, equipment and personnel with the required qualifications. Onshore facilities and access logistics (i.e. crew vessel) will be provided by the …